Project | JJM PHASE- II (2021-24) - CWSS to Ambalavayal, Nenmeni, Poothady and Pulpally GP- Providing FHTCs in AMBALAVAYAL Panchayath |
---|---|
Project Code | WYDJJM022212434P1 |
Type | Package |
Main Project | JJM PHASE II (2021-22) CWSS to Ambalavayal, Nenmeni, Poothady and Pulpally GP- Providing FHTCs in AMBALAVAYAL Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Augmentation of WSS and providing FHTC's in Ambalavayal Grama Panchayath |
Status | On-going |
District | Wayanad |
Executing Office | Sulthan Bathery Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 5751000000 |
TS Number | TS/1304/2022_26_1_1 |
Technical specification | NIL |
Contractor | T ABDUSSAMAD (Mob: 9745850000) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/01/2023 |
---|---|
Scheduled date of Completion as per agreement | 20 Jan 2024 |
Expected date of Completion | 31/03/2025 |
TS Date | 31 Oct 2022 |
---|---|
Estimate Approval | 31 Oct 2022 |
NIT Approval | 30 Aug 2022 |
Tender Closing | 20 Aug 2022 |
Technichal Pre-Qualification | 20 Sep 2022 |
Price bid opening | 20 Sep 2022 |
Workorder Date | 31 Oct 2022 |
---|---|
NA | 04 Feb 2023 |
Sulthan Bathery PH Sn - AE |
Date: 26/06/2024 |
Work in progress | 56% Completed
13 LL Ambalavayal OHSR tank wall 1 M RCC Work completed, No Work due to rain.
Sulthan Bathery PH Sn - AE |
Date: 18/06/2024 |
Work in progress | 56% Completed
13 LL Ambalavayal OHSR tank wall 1 M RCC Work completed.