JJM PHASE- II (2021-24) - CWSS to Ambalavayal, Nenmeni, Poothady and Pulpally GP- Providing FHTCs in AMBALAVAYAL Panchayath

Project JJM PHASE- II (2021-24) - CWSS to Ambalavayal, Nenmeni, Poothady and Pulpally GP- Providing FHTCs in AMBALAVAYAL Panchayath
Project Code WYDJJM022212434P1
Type Package
Main Project JJM PHASE II (2021-22) CWSS to Ambalavayal, Nenmeni, Poothady and Pulpally GP- Providing FHTCs in AMBALAVAYAL Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Augmentation of WSS and providing FHTC's in Ambalavayal Grama Panchayath
Status On-going
District Wayanad
Executing Office Sulthan Bathery Sn
Agreement Number
Agreement Date
TS Amount (Rs) 5751000000
TS Number TS/1304/2022_26_1_1
Technical specification NIL
Contractor T ABDUSSAMAD (Mob: 9745850000)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 21/01/2023
Scheduled date of Completion as per agreement 20 Jan 2024
Expected date of Completion 31/03/2025

Processing Dates

TS Date 31 Oct 2022
Estimate Approval 31 Oct 2022
NIT Approval 30 Aug 2022
Tender Closing 20 Aug 2022
Technichal Pre-Qualification 20 Sep 2022
Price bid opening 20 Sep 2022

Approval Dates

Workorder Date 31 Oct 2022
NA 04 Feb 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sulthan Bathery PH Sn - AE
Date: 26/06/2024

Work in progress | 56% Completed

13 LL Ambalavayal OHSR tank wall 1 M RCC Work completed, No Work due to rain.

Sulthan Bathery PH Sn - AE
Date: 18/06/2024

Work in progress | 56% Completed

13 LL Ambalavayal OHSR tank wall 1 M RCC Work completed.