Chavara AE
Date: 19/11/2024

Work has been completed | 100% Completed

Work started on 03.09.2024. 365 public taps disconnected

Chavara AE
Date: 16/11/2024

Work in progress | 95% Completed

Work started on 03.09.2024. 365 public taps disconnected

Chavara AE
Date: 14/11/2024

Work in progress | 95% Completed

Work started on 03.09.2024. 365 public taps disconnected

Chavara AE
Date: 11/11/2024

Work in progress | 95% Completed

Work started on 03.09.2024. 365 public taps disconnected

Chavara AE
Date: 05/11/2024

Work in progress | 95% Completed

Work started on 03.09.2024. 365 public taps disconnected

Chavara AE
Date: 02/11/2024

Work in progress | 95% Completed

Work started on 03.09.2024. 365 public taps disconnected

Chavara AE
Date: 30/10/2024

Work in progress | 95% Completed

Work started on 03.09.2024. 365 public taps disconnected

Chavara AE
Date: 28/10/2024

Work in progress | 95% Completed

Work started on 03.09.2024. 365 public taps disconnected

Chavara AE
Date: 21/10/2024

Work in progress | 82% Completed

Work started on 03.09.2024. 313 public taps disconnected

Chavara AE
Date: 17/10/2024

Work in progress | 82% Completed

Work started on 03.09.2024. 313 public taps disconnected

Chavara AE
Date: 13/10/2024

Work in progress | 80% Completed

Work started on 03.09.2024. 303 public taps disconnected

Chavara AE
Date: 09/10/2024

Work in progress | 80% Completed

Work started on 03.09.2024. 303 public taps disconnected

Chavara AE
Date: 06/10/2024

Work in progress | 80% Completed

Work started on 03.09.2024. 303 public taps disconnected

Chavara AE
Date: 02/10/2024

Work in progress | 80% Completed

Work started on 03.09.2024. 303 public taps disconnected

Chavara AE
Date: 29/09/2024

Work in progress | 80% Completed

Work started on 03.09.2024. 303 public taps disconnected

Chavara AE
Date: 26/09/2024

Work in progress | 80% Completed

Work started on 03.09.2024. 295 public taps disconnected

Chavara AE
Date: 23/09/2024

Work in progress | 80% Completed

Work started on 03.09.2024. 295 public taps disconnected

Chavara AE
Date: 18/09/2024

Work in progress | 76% Completed

Work started on 03.09.2024. 273 public taps disconnected

Chavara AE
Date: 10/09/2024

Work in progress | 49% Completed

Work started on 03.09.2024. 190 public taps disconnected

Chavara AE
Date: 07/09/2024

Work in progress | 29% Completed

Work started on 03.09.2024. 136 public taps disconnected

Chavara AE
Date: 04/09/2024

Work in progress | 15% Completed

Work started on 03.09.2024. 81 public taps disconnected

Chavara AE
Date: 02/09/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 30/08/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 27/08/2024

Work in progress | 1% Completed

Work in progress

Chavara AE
Date: 21/08/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 17/08/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 14/08/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 11/08/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 08/08/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 05/08/2024

Work in progress | 1% Completed

Work in progress

Chavara AE
Date: 02/08/2024

Work in progress | 1% Completed

Work in progress

Chavara AE
Date: 30/07/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 27/07/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 24/07/2024

Work in progress | 1% Completed

Work order issued

Chavara AE
Date: 21/07/2024

Work in progress | 1% Completed

Bid evaluation on going

Chavara AEE
Date: 18/07/2024

Work in progress | 1% Completed

Bid evaluation ongoing

Chavara AE
Date: 15/07/2024

Work in progress | 1% Completed

Bid evaluation ongoing

Chavara AE
Date: 12/07/2024

Work in progress | 1% Completed

work under tender processing

Chavara AE
Date: 08/07/2024

Work in progress | 1% Completed

work under tender processing

Chavara AE
Date: 05/07/2024

Work in progress | 1% Completed

work under tender processing

Chavara AE
Date: 02/07/2024

Work in progress | 1% Completed

work under tender processing

Chavara AE
Date: 29/06/2024

Work in progress | 1% Completed

work under tender processing

Chavara AE
Date: 26/06/2024

Work in progress | 1% Completed

work under tender processing

Chavara AE
Date: 23/06/2024

Work in progress | 1% Completed

work under tender processing

Chavara AE
Date: 20/06/2024

Work in progress | 1% Completed

work under tender processing

Chavara AE
Date: 17/06/2024

Work in progress | 1% Completed

work under tender processing

Chavara AEE
Date: 13/06/2024

Work in progress | 1% Completed

work under tender processing