DEPOSIT-RWSS TO THODIYOORDISCONNECTION OF STREET TAP AT VARIOUS WARDS IN THODIYOOR PANCHAYATH-RWSS TO THODIYOORDISCONNECTION OF STREET TAP AT VARIOUS WARDS IN THODIYOOR PANCHAYATH-General Civil Work

Project DEPOSIT-RWSS TO THODIYOORDISCONNECTION OF STREET TAP AT VARIOUS WARDS IN THODIYOOR PANCHAYATH-RWSS TO THODIYOORDISCONNECTION OF STREET TAP AT VARIOUS WARDS IN THODIYOOR PANCHAYATH-General Civil Work
Project Code KLMDEPO112315968P1
Type Package
Main Project DEPOSIT-RWSS TO THODIYOORDISCONNECTION OF STREET TAP AT VARIOUS WARDS IN THODIYOOR PANCHAYATH-RWSS TO THODIYOORDISCONNECTION OF STREET TAP AT VARIOUS WARDS IN THODIYOOR PANCHAYATH-General Civil Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-RWSS TO THODIYOORDISCONNECTION OF STREET TAP AT VARIOUS WARDS IN THODIYOOR PANCHAYATH-RWSS TO THODIYOORDISCONNECTION OF STREET TAP AT VARIOUS WARDS IN THODIYOOR PANCHAYATH-General Civil Work
Status On-going
District Kollam
Executing Office Chavara PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 767000
TS Number WRD/KWA-CE(SR)/EST_TS/10618/2023_5_2_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 13 May 2024
Estimate Approval 10 May 2024
NIT Approval 10 Jun 2024
Tender Closing 20 Jun 2024
Price bid opening 21 Jun 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chavara AE
Date: 19/11/2024

Work has been completed | 100% Completed

Work started on 03.09.2024. 365 public taps disconnected.

Chavara AE
Date: 16/11/2024

Work in progress | 95% Completed

Work started on 03.09.2024. 365 public taps disconnected.