| Kollam WS Sn 2 - AE |
| Date: 23/06/2023 |
Work has been completed | 100% Completed
100 % work completed
| Kollam WS Sn 2 - AE |
| Date: 20/06/2023 |
Work in progress | 95% Completed
95 % completed, restoration of concrete work to be done.
| Kollam WS Sn 2 - AE |
| Date: 16/06/2023 |
Work in progress | 95% Completed
95 % completed, restoration of concrete work to be done.
| Kollam WS Sn 2 - AE |
| Date: 12/06/2023 |
Work in progress | 25% Completed
Work started 11/6/2023 ( concrete demolishing), pipe laying works started 12/6/2023 and 25 % completed
| Kollam WS Sn 2 - AE |
| Date: 09/06/2023 |
Work in progress | 0% Completed
Site handed over and work will start soon
| Kollam WS Sn 2 - AE |
| Date: 05/06/2023 |
Work in progress | 0% Completed
tested pipe not get
| Kollam WS Sn 2 - AE |
| Date: 01/06/2023 |
Work in progress | 0% Completed
tested pipe not get
| Kollam WS Sn 2 - AE |
| Date: 29/05/2023 |
Work in progress | 0% Completed
tested pipe not get
| Kollam WS Sn 2 - AE |
| Date: 24/05/2023 |
Work in progress | 0% Completed
tested pipe not get
| Kollam WS Sn 2 - AE |
| Date: 19/05/2023 |
Work in progress | 0% Completed
Tested pipe not get
| Kollam WS Sn 2 - AE |
| Date: 15/05/2023 |
Work has started | 0% Completed
LOA generated and sent to contractor
| Kollam WS Sn 2 - AE |
| Date: 08/05/2023 |
Work in progress | 0% Completed
LOA generated
| Kollam WS Sn 2 - AE |
| Date: 05/05/2023 |
Work has started | 0% Completed
LOA generated
| Kollam WS Sub Dn - AEE |
| Date: 04/05/2023 |
Work has started | 0% Completed
LOA CREATED