Deposit work Kollam Corporation -Urban Agglomeration-Extension of 75mm PVC pipe line at Venkekara road to Penayezhikathu area of Mathilil division No.11 of kollam Corporation.-Pipeline Work

Project Deposit work Kollam Corporation -Urban Agglomeration-Extension of 75mm PVC pipe line at Venkekara road to Penayezhikathu area of Mathilil division No.11 of kollam Corporation.-Pipeline Work
Project Code KLMDEPO032314017P1
Type Package
Main Project Deposit work Kollam Corporation -Urban Agglomeration-Extension of 75mm PVC pipe line at Venkekara road to Penayezhikathu area of Mathilil division No.11 of kollam Corporation.-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work Kollam Corporation -Urban Agglomeration-Extension of 75mm PVC pipe line at Venkekara road to Penayezhikathu area of Mathilil division No.11 of kollam Corporation.-Pipeline Work
Status On-going
District Kollam
Executing Office Kollam WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 154000
TS Number WRD/KWA-CE(SR)/EST_TS/7252/2023_26_1_1
Technical specification Extension of 75mm PVC pipe line at Venkekara road to Penayezhikathu area of Mathilil division No.11 of kollam Corporation.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/03/2023
Scheduled date of Completion as per agreement 31 May 2023
Expected date of Completion 15/06/2023

Processing Dates

TS Date 10 Apr 2023
Estimate Approval 10 Apr 2023
NIT Approval 10 Apr 2023
Tender Closing 28 Apr 2023
Technichal Pre-Qualification 28 Apr 2023
Price bid opening 29 Apr 2023

Approval Dates

Workorder Date 02 May 2023
NA 15 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam WS Sn 2 - AE
Date: 23/06/2023

Work has been completed | 100% Completed

100 % work completed.

Kollam WS Sn 2 - AE
Date: 20/06/2023

Work in progress | 95% Completed

95 % completed, restoration of concrete work to be done..