| Kollam WS Sn 2 - AE |
| Date: 13/09/2024 |
Work has been completed | 100% Completed
Work completed, Final bill submitted
| Kollam WS Sn 2 - AE |
| Date: 02/09/2024 |
Work has been completed | 100% Completed
Work completed, 347nos of tap disconnected, Bill under preparation
| Kollam WS Sn 2 - AE |
| Date: 29/08/2024 |
Work has been completed | 100% Completed
Work completed, 347nos of tap disconnected, Bill under preparation
| Kollam WS Sn 2 - AE |
| Date: 22/08/2024 |
Work in progress | 99% Completed
Work completed, 347nos of tap disconnected, Bill under preparation
| Kollam WS Sn 2 - AE |
| Date: 16/08/2024 |
Work in progress | 97% Completed
Work in progress, 339 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 13/08/2024 |
Work in progress | 90% Completed
Work in progress, 315 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 10/08/2024 |
Work in progress | 88% Completed
Work in progress
| Kollam WS Sn 2 - AE |
| Date: 06/08/2024 |
Work in progress | 88% Completed
Work in progress, 306 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 01/08/2024 |
Work in progress | 86% Completed
Work in progress, 300 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 29/07/2024 |
Work in progress | 86% Completed
Work in progress, 300 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 25/07/2024 |
Work in progress | 79% Completed
Work in progress, 280 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 22/07/2024 |
Work in progress | 79% Completed
Work in progress, 280 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 18/07/2024 |
Work in progress | 66% Completed
Work in progress, 260 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 15/07/2024 |
Work in progress | 65% Completed
Work in progress, 236 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 12/07/2024 |
Work in progress | 65% Completed
Work in progress, 236 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 09/07/2024 |
Work in progress | 65% Completed
Work in progress, 235 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 05/07/2024 |
Work in progress | 65% Completed
Work in progress, 221 nos out of 347 completed
| Kollam WS Sn 2 - AE |
| Date: 02/07/2024 |
Work in progress | 64% Completed
221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors .
| Kollam WS Sn 2 - AE |
| Date: 29/06/2024 |
Work in progress | 64% Completed
221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors .
| Kollam WS Sn 2 - AE |
| Date: 26/06/2024 |
Work in progress | 64% Completed
64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors .
| Kollam WS Sn 2 - AE |
| Date: 24/06/2024 |
Work in progress | 64% Completed
64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors .
| Kollam WS Sn 2 - AE |
| Date: 19/06/2024 |
Work in progress | 64% Completed
64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors .
| Kollam WS Sn 2 - AE |
| Date: 15/06/2024 |
Work in progress | 64% Completed
64 % disconnected - 221 nos out of 347 nos.completed. Balance taps as per list cannot locate, hence copy of list forwarded to the concerned division councilors .
| Kollam WS Sn 2 - AE |
| Date: 14/06/2024 |
Work in progress | 64% Completed
64 % disconnected - 221 nos out of 347 nos.completed.
| Kollam WS Sn 2 - AE |
| Date: 10/06/2024 |
Work in progress | 64% Completed
Work restarted, But due to water logging area excavation is difficult and affects the progress of work. Package 2- 64 % disconnected - 221 nos out of 347 nos.completed.
| Kollam WS Sn 2 - AE |
| Date: 05/06/2024 |
Work in progress | 55% Completed
Work restarted, But due to water logging area excavation is difficult and affects the progress of work. package 2- 55 % disconnected - 191 nos out of 347 nos.completed.
| Kollam WS Sn 2 - AE |
| Date: 01/06/2024 |
Work in progress | 50% Completed
Due to continuous rain and heavy water logged areas , exception is not possible. Hence Work not possible.Time of extension application submitted.
| Kollam WS Sn 2 - AE |
| Date: 28/05/2024 |
Work in progress | 50% Completed
Due to heavy and continuous rain work progress is slow. Huge interruptions are raised from public and they not allow to cut the street tap. This matter informed to Dn. Councilor, Deputy mayor.
| Kollam WS Sn 2 - AE |
| Date: 25/05/2024 |
Work in progress | 44% Completed
Work started, but huge interruptions are raised from public and they not allow to cut the street tap. This matter informed to Dn. Councilor, Deputy mayor.
| Kollam WS Sn 2 - AE |
| Date: 21/05/2024 |
Work in progress | 43% Completed
Street tap disconnection works restarted.
| Kollam WS Sn 2 - AE |
| Date: 17/05/2024 |
Work in progress | 43% Completed
Work temporarily stopped considering drought and oral direction from Mayor, Kollam corporation
| Kollam WS Sn 2 - AE |
| Date: 13/05/2024 |
Work in progress | 43% Completed
Work temporarily stopped considering drought and oral direction from Mayor, Kollam corporation .
| Kollam WS Sn 2 - AE |
| Date: 08/05/2024 |
Work in progress | 43% Completed
Work temporarily stopped considering drought and oral direction from Mayor, Kollam corporation .
| Kollam WS Sn 2 - AE |
| Date: 04/05/2024 |
Work in progress | 43% Completed
Work temporarily stopped considering drought and oral direction from Mayor, Kollam corporation .
| Kollam WS Sn 2 - AE |
| Date: 30/04/2024 |
Work in progress | 43% Completed
Work temporarily stopped considering drought and oral direction from Mayor, Kollam corporation
| Kollam WS Sn 2 - AE |
| Date: 27/04/2024 |
Work in progress | 43% Completed
Work temporarily stopped considering drought and oral direction from Mayor, Kollam corporation .
| Kollam WS Sn 2 - AE |
| Date: 24/04/2024 |
Work in progress | 43% Completed
Work tempaorarily stopped considering drought and oral direction from Mayor, Kollam corporartion .
| Kollam WS Sn 2 - AE |
| Date: 20/04/2024 |
Work in progress | 43% Completed
Work tempaorarily stopped considering drought and oral direction from Mayor, Kollam corporartion .
| Kollam WS Sn 2 - AE |
| Date: 16/04/2024 |
Work in progress | 43% Completed
Work tempaorarily stopped considering drought and oral direction from Mayor, Kollam corporartion .
| Kollam WS Sn 2 - AE |
| Date: 12/04/2024 |
Work in progress | 43% Completed
Work tempaorarily stopped considering drought and oral direction from Mayor, Kollam corporartion .
| Kollam WS Sn 2 - AE |
| Date: 09/04/2024 |
Work in progress | 43% Completed
Work tempaorarily stopped considering drought and oral direction from Mayor, Kollam corporartion .
| Kollam WS Sn 2 - AE |
| Date: 05/04/2024 |
Work in progress | 43% Completed
Work tempaorarily stopped considering drought and oral direction from Mayor, Kollam corporartion .
| Kollam WS Sn 2 - AE |
| Date: 01/04/2024 |
Work in progress | 43% Completed
Work tempaorarily stopped considering drought and requests from councilors.
| Kollam WS Sn 2 - AE |
| Date: 25/03/2024 |
Work in progress | 43% Completed
PACKAGE I- 150 Nos. tap disconnected. 43% COMPLETED), interruption by public arisen due to severe drought. Disconnection temporarily stopped considering drought and requests from councilors. PACKAGE 2-40 % COMPLETED ( 170 NOS. OF TAP DISCONNECTED )
| Kollam WS Sn 2 - AE |
| Date: 21/03/2024 |
Work in progress | 43% Completed
PACKAGE I- 150 Nos. tap disconnected. 43% COMPLETED), interruption by public arisen due to severe drought. Disconnection temporarily stopped considering drought and requests from councilors.
| Kollam WS Sn 2 - AE |
| Date: 15/03/2024 |
Work in progress | 34% Completed
PACKAGE 1- 120 Nos. taps disconected. 34 % completed. Work interrupts by Public and consumers due to severe drought.
| Kollam WS Sn 2 - AE |
| Date: 11/03/2024 |
Work in progress | 2% Completed
PACKAGE 1- SITE HANDED OVER and work started( 2% COMPLETED), interruption by public arisen due to severe drought.
| Kollam WS Sn 2 - AE |
| Date: 01/03/2024 |
Work in progress | 1% Completed
SITE HANDED OVER and disconnection list given( 1 % COMPLETED.
| Kollam WS Sn 2 - AE |
| Date: 26/02/2024 |
Work in progress | 1% Completed
SITE HANDED OVER and disconnection list given( 1 % COMPLETED.
| Kollam WS Sn 2 - AE |
| Date: 21/02/2024 |
Work in progress | 1% Completed
SITE HANDED OVER and disconnection list given( 1 % COMPLETED.
| Kollam WS Sn 2 - AE |
| Date: 17/02/2024 |
Work in progress | 1% Completed
SITE HANDED OVER and disconnection list given( 1 % COMPLETED.
| Kollam WS Sub Dn - AEE |
| Date: 15/02/2024 |
Work in progress | 1% Completed
SITE HANDED OVER
| Kollam WS Sub Dn - AEE |
| Date: 14/02/2024 |
Work in progress | 1% Completed
work started