| Project | DEPOSIT-QWSS- Disconnection of Public Taps under Sakthikulangara and Thrikkadavoor area of Kollam Corporation -Pipeline Work |
|---|---|
| Project Code | KLMDEPO112315576P2 |
| Type | Package |
| Main Project | DEPOSIT-QWSS- Disconnection of Public Taps under Sakthikulangara and Thrikkadavoor area of Kollam Corporation -Pipeline Work |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | DEPOSIT-QWSS- Disconnection of Public Taps under Sakthikulangara and Thrikkadavoor area of Kollam Corporation -Pipeline Work |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam WS Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 420000 |
| TS Number | WRD/KWA-CE(SR)/EST_TS/23918/2023_26_1_1 |
| Technical specification | Sakthikulangara and Thrikkadavoor area |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 11/11/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 27 Jan 2024 |
| Expected date of Completion | 27/01/2024 |
| TS Date | 18 Nov 2023 |
|---|---|
| Estimate Approval | 07 Nov 2023 |
| NIT Approval | 07 Nov 2023 |
| Tender Closing | 27 Nov 2023 |
| Technichal Pre-Qualification | 27 Nov 2023 |
| Price bid opening | 28 Nov 2023 |
| Workorder Date | 14 Dec 2023 |
|---|---|
| NA | 28 Dec 2023 |
| Kollam WS Sn 2 - AE |
| Date: 13/09/2024 |
Work has been completed | 100% Completed
Work completed, Final bill submitted.
| Kollam WS Sn 2 - AE |
| Date: 02/09/2024 |
Work has been completed | 100% Completed
Work completed, 347nos of tap disconnected, Bill under preparation.