| Oachira AE |
| Date: 17/07/2026 |
Work in progress | 35% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed. Panel board fixing work ongoing.
| Oachira AE |
| Date: 15/07/2026 |
Work in progress | 35% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed. Panel board fixing work ongoing.
| Oachira AE |
| Date: 13/07/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 10/07/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 06/07/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 01/07/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 29/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 24/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 22/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 18/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 15/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 12/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 08/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 06/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 03/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 01/06/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 29/05/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 27/05/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 25/05/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 23/05/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 20/05/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 18/05/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 16/05/2026 |
Work in progress | 30% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.
| Oachira AE |
| Date: 15/05/2026 |
| Oachira AE |
| Date: 13/05/2026 |
Work in progress | 20% Completed
Panel board work ongoing
| Oachira AE |
| Date: 11/05/2026 |
Work in progress | 20% Completed
Panel board work ongoing
| Oachira AE |
| Date: 07/05/2026 |
Work in progress | 20% Completed
Panel board work ongoing
| Oachira AE |
| Date: 04/05/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 02/05/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 30/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 28/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 25/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 23/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 21/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 18/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 16/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 13/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 10/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 08/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 07/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 06/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 04/04/2026 |
Work in progress | 20% Completed
Panel board work ongoing, ELCB fixed
| Oachira AE |
| Date: 01/04/2026 |
| Oachira AE |
| Date: 30/03/2026 |
Work in progress | 10% Completed
Pannelboard fitting work ongoing and application for KSEB Connection submitted
| Oachira AE |
| Date: 28/03/2026 |
Work in progress | 10% Completed
Pannelboard fitting work ongoing and application for KSEB Connection submitted