Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Oachira AE
Date: 17/07/2026

Work in progress | 35% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed. Panel board fixing work ongoing.

Oachira AE
Date: 15/07/2026

Work in progress | 35% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed. Panel board fixing work ongoing.

Oachira AE
Date: 13/07/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 10/07/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 06/07/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 01/07/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 29/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 24/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 22/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 18/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 15/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 12/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 08/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 06/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 03/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 01/06/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 29/05/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 27/05/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 25/05/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 23/05/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 20/05/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 18/05/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 16/05/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Oachira AE
Date: 15/05/2026

Work in progress | 30% Completed

Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed.

Attached images

img

Oachira AE
Date: 13/05/2026

Work in progress | 20% Completed

Panel board work ongoing

Oachira AE
Date: 11/05/2026

Work in progress | 20% Completed

Panel board work ongoing

Oachira AE
Date: 07/05/2026

Work in progress | 20% Completed

Panel board work ongoing

Oachira AE
Date: 04/05/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 02/05/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 30/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 28/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 25/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 23/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 21/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 18/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 16/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 13/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 10/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 08/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 07/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 06/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 04/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Oachira AE
Date: 01/04/2026

Work in progress | 20% Completed

Panel board work ongoing, ELCB fixed

Attached images

img

Oachira AE
Date: 30/03/2026

Work in progress | 10% Completed

Pannelboard fitting work ongoing and application for KSEB Connection submitted

Oachira AE
Date: 28/03/2026

Work in progress | 10% Completed

Pannelboard fitting work ongoing and application for KSEB Connection submitted