DEPOSIT-CWSS to Oachira, Karuanagappally, Alappad and Clappana- Interconnection of pumping main with distribution lines, Pump house wiring, Automation of pump house, Chlorination arrangements etc. at pump house constructed near CFA ground in ward no.10 of Alappad Panchayath.-General Civil Work
| Project |
DEPOSIT-CWSS to Oachira, Karuanagappally, Alappad and Clappana- Interconnection of pumping main with distribution lines, Pump house wiring, Automation of pump house, Chlorination arrangements etc. at pump house constructed near CFA ground in ward no.10 of Alappad Panchayath.-General Civil Work |
| Project Code |
KLMDEPO072518208P1 |
| Type |
Package |
| Main Project |
DEPOSIT-CWSS to Oachira, Karuanagappally, Alappad and Clappana- Interconnection of pumping main with distribution lines, Pump house wiring, Automation of pump house, Chlorination arrangements etc. at pump house constructed near CFA ground in ward no.10 of Alappad Panchayath.-General Civil Work
|
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
DEPOSIT-CWSS to Oachira, Karuanagappally, Alappad and Clappana- Interconnection of pumping main with distribution lines, Pump house wiring, Automation of pump house, Chlorination arrangements etc. at pump house constructed near CFA ground in ward no.10 of Alappad Panchayath.-General Civil Work |
| Status |
On-going |
| District |
Kollam |
| Executing Office |
Oachira PH Sn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
283000 |
| TS Number |
WRD/KWA-CE(SR)/EST_TS/9197/2025_5_1_1 |
| Technical specification |
|
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
Date is not specified |
| Scheduled date of Completion as per agreement |
09 Feb 2026 |
| Expected date of Completion |
09/02/2026 |
Processing Dates
| TS Date |
09 Sep 2025 |
| Estimate Approval |
10 Apr 2025 |
| NIT Approval |
09 Sep 2025 |
| Tender Closing |
17 Sep 2025 |
Approval Dates
| Workorder Date |
15 Mar 2025 |
| NA |
31 Dec 2025 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Oachira AE |
| Date: 17/07/2026 |
Work in progress | 35% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed. Panel board fixing work ongoing..
| Oachira AE |
| Date: 15/07/2026 |
Work in progress | 35% Completed
Pipe laying (110 mm PVC pipe - 45 m) and interconnection works completed. Panel board fixing work ongoing..