Cheruvathur AE |
Date: 02/02/2023 |
Work has been completed | 100% Completed
work completed final bill submitted
Cheruvathur AE |
Date: 11/11/2022 |
Work has been completed | 100% Completed
Work completed
Cheruvathur AE |
Date: 26/10/2022 |
Work has been completed | 100% Completed
Work completed
Cheruvathur AE |
Date: 17/10/2022 |
Work in progress | 90% Completed
pipe line work in progress.250nos out of 250 of connection physically completed and 200 nos geotagged
Cheruvathur AE |
Date: 13/10/2022 |
Work in progress | 90% Completed
pipe line work in progress.250nos out of 250 of connection physically completed and 200 nos geotagged
Cheruvathur AE |
Date: 10/10/2022 |
Work in progress | 90% Completed
pipe line work in progress.250nos out of 250 of connection physically completed and 200 nos geotagged
Cheruvathur AE |
Date: 03/10/2022 |
Work in progress | 71% Completed
pipe line work in progress.230nos out of 250 of connection physically completed and 123 nos geotagged
Cheruvathur AE |
Date: 26/09/2022 |
Work in progress | 70% Completed
pipe line work in progress.230nos out of 250 of connection physically completed and 123 nos geotagged
Cheruvathur AE |
Date: 22/09/2022 |
Work in progress | 70% Completed
pipe line work in progress.230nos out of 250 of connection physically completed and 123 nos geotagged
Cheruvathur AE |
Date: 16/09/2022 |
Work in progress | 70% Completed
pipe line work in progress.230nos out of 250 of connection physically completed and 123 nos geotagged
Cheruvathur AE |
Date: 12/09/2022 |
Work in progress | 50% Completed
pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos
Cheruvathur AE |
Date: 06/09/2022 |
Work in progress | 50% Completed
pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos
Cheruvathur AE |
Date: 01/09/2022 |
Work in progress | 50% Completed
pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos
Cheruvathur AE |
Date: 27/08/2022 |
Work in progress | 50% Completed
pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos
Cheruvathur AE |
Date: 22/08/2022 |
Work in progress | 50% Completed
pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos
Cheruvathur AE |
Date: 16/08/2022 |
Work in progress | 42% Completed
pipe line work in progress
Cheruvathur AE |
Date: 13/08/2022 |
Work in progress | 42% Completed
pipe line work in progress
Cheruvathur AE |
Date: 08/08/2022 |
Work in progress | 41% Completed
pipe line work in progress
Cheruvathur AE |
Date: 04/08/2022 |
Work in progress | 41% Completed
pipe line work in progress
Cheruvathur AE |
Date: 02/08/2022 |
Work in progress | 41% Completed
work restarted
Cheruvathur AE |
Date: 25/07/2022 |
Work in progress | 41% Completed
work temporarily stopped due to heavy rain.
Cheruvathur AE |
Date: 19/07/2022 |
Work in progress | 41% Completed
work temporarily stopped due to heavy rain.
Cheruvathur AE |
Date: 13/07/2022 |
Work in progress | 41% Completed
temporarily stopped due to heavy rain.
Cheruvathur AE |
Date: 04/07/2022 |
Work in progress | 41% Completed
Pipe laying work is progressing on .120 nos FHTC is physically done,geo tagging is pending. work is temporarily stopped due to heavy rain
Cheruvathur AE |
Date: 25/06/2022 |
Work in progress | 40% Completed
Pipe laying work is progressing on .120 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work
Cheruvathur AE |
Date: 17/06/2022 |
Work in progress | 37% Completed
pipe laying work is progressing on .110 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.
Cheruvathur AE |
Date: 13/06/2022 |
Work in progress | 36% Completed
pipe laying work is progressing on .100 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.
Cheruvathur AE |
Date: 07/06/2022 |
Work in progress | 34% Completed
pipe laying work is progressing on .100 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.
Cheruvathur AE |
Date: 27/05/2022 |
Work in progress | 31% Completed
pipe laying work is progressing on .100 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.
Cheruvathur AE |
Date: 22/05/2022 |
Work in progress | 30% Completed
pipe laying work is progressing on .100 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.
Cheruvathur AE |
Date: 18/05/2022 |
Work in progress | 23% Completed
WORK IN PROGRESS
Cheruvathur AE |
Date: 10/05/2022 |
Work in progress | 23% Completed
WORK IN PROGRESS
Cheruvathur AE |
Date: 04/05/2022 |
Work in progress | 21% Completed
WORK IN PROGRESS
Cheruvathur AE |
Date: 30/04/2022 |
Work in progress | 20% Completed
90mm PVC pipe supplied .work in progress
Cheruvathur AE |
Date: 20/04/2022 |
Work in progress | 17% Completed
Due to not supply the PVC pipes work is held up.
Cheruvathur AE |
Date: 12/04/2022 |
Work in progress | 17% Completed
Due to not supply the PVC pipes work is held up.
Cheruvathur AE |
Date: 04/04/2022 |
Work in progress | 17% Completed
Due to not supply the PVC pipes work is held up.
Cheruvathur AE |
Date: 01/04/2022 |
Work in progress | 17% Completed
Due to not supply the PVC pipes work is held up.
Cheruvathur AE |
Date: 28/03/2022 |
Work in progress | 17% Completed
Due to not supply the PVC pipes work is held up.
Cheruvathur AE |
Date: 22/03/2022 |
Work in progress | 17% Completed
Due to not supply the PVC pipes work is held up.
Cheruvathur AE |
Date: 13/03/2022 |
Work in progress | 17% Completed
Due to not supply the PVC pipes work is held up.
Cheruvathur AE |
Date: 12/03/2022 |
Work in progress | 17% Completed
PVC pipe is not supplied,earth work excavation progressing
Cheruvathur AE |
Date: 08/03/2022 |
Work in progress | 16% Completed
PVC pipe is not supplied,earth work excavation progressing
Cheruvathur AE |
Date: 04/03/2022 |
Work in progress | 16% Completed
PVC pipe is not supplied,earth work excavation progressing
Cheruvathur AE |
Date: 28/02/2022 |
Work in progress | 15% Completed
PVC pipe is not supplied,earth work excavation progressing
Cheruvathur AE |
Date: 21/02/2022 |
Cheruvathur AE |
Date: 15/02/2022 |
Work in progress | 2% Completed
PVC pipe is not supplied
Cheruvathur AE |
Date: 14/02/2022 |
Work in progress | 2% Completed
PVC pipe is not supplied
Cheruvathur AE |
Date: 10/02/2022 |
Work in progress | 2% Completed
PVC pipe is not supplied
Cheruvathur AE |
Date: 03/02/2022 |
Work in progress | 2% Completed
PVC pipe is not supplied
Cheruvathur AE |
Date: 01/02/2022 |
Work in progress | 2% Completed
PVC pipe is not supplied