Cheruvathur AE
Date: 02/02/2023

Work has been completed | 100% Completed

work completed final bill submitted

Cheruvathur AE
Date: 11/11/2022

Work has been completed | 100% Completed

Work completed

Cheruvathur AE
Date: 26/10/2022

Work has been completed | 100% Completed

Work completed

Cheruvathur AE
Date: 17/10/2022

Work in progress | 90% Completed

pipe line work in progress.250nos out of 250 of connection physically completed and 200 nos geotagged

Cheruvathur AE
Date: 13/10/2022

Work in progress | 90% Completed

pipe line work in progress.250nos out of 250 of connection physically completed and 200 nos geotagged

Cheruvathur AE
Date: 10/10/2022

Work in progress | 90% Completed

pipe line work in progress.250nos out of 250 of connection physically completed and 200 nos geotagged

Cheruvathur AE
Date: 03/10/2022

Work in progress | 71% Completed

pipe line work in progress.230nos out of 250 of connection physically completed and 123 nos geotagged

Cheruvathur AE
Date: 26/09/2022

Work in progress | 70% Completed

pipe line work in progress.230nos out of 250 of connection physically completed and 123 nos geotagged

Cheruvathur AE
Date: 22/09/2022

Work in progress | 70% Completed

pipe line work in progress.230nos out of 250 of connection physically completed and 123 nos geotagged

Cheruvathur AE
Date: 16/09/2022

Work in progress | 70% Completed

pipe line work in progress.230nos out of 250 of connection physically completed and 123 nos geotagged

Cheruvathur AE
Date: 12/09/2022

Work in progress | 50% Completed

pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos

Cheruvathur AE
Date: 06/09/2022

Work in progress | 50% Completed

pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos

Cheruvathur AE
Date: 01/09/2022

Work in progress | 50% Completed

pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos

Cheruvathur AE
Date: 27/08/2022

Work in progress | 50% Completed

pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos

Cheruvathur AE
Date: 22/08/2022

Work in progress | 50% Completed

pipe line work in progress.127nos of connection physically completed and 123 nos geotagged and imis entry out of 250nos

Cheruvathur AE
Date: 16/08/2022

Work in progress | 42% Completed

pipe line work in progress

Cheruvathur AE
Date: 13/08/2022

Work in progress | 42% Completed

pipe line work in progress

Cheruvathur AE
Date: 08/08/2022

Work in progress | 41% Completed

pipe line work in progress

Cheruvathur AE
Date: 04/08/2022

Work in progress | 41% Completed

pipe line work in progress

Cheruvathur AE
Date: 02/08/2022

Work in progress | 41% Completed

work restarted

Cheruvathur AE
Date: 25/07/2022

Work in progress | 41% Completed

work temporarily stopped due to heavy rain.

Cheruvathur AE
Date: 19/07/2022

Work in progress | 41% Completed

work temporarily stopped due to heavy rain.

Cheruvathur AE
Date: 13/07/2022

Work in progress | 41% Completed

temporarily stopped due to heavy rain.

Cheruvathur AE
Date: 04/07/2022

Work in progress | 41% Completed

Pipe laying work is progressing on .120 nos FHTC is physically done,geo tagging is pending. work is temporarily stopped due to heavy rain

Cheruvathur AE
Date: 25/06/2022

Work in progress | 40% Completed

Pipe laying work is progressing on .120 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work

Cheruvathur AE
Date: 17/06/2022

Work in progress | 37% Completed

pipe laying work is progressing on .110 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.

Cheruvathur AE
Date: 13/06/2022

Work in progress | 36% Completed

pipe laying work is progressing on .100 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.

Cheruvathur AE
Date: 07/06/2022

Work in progress | 34% Completed

pipe laying work is progressing on .100 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.

Cheruvathur AE
Date: 27/05/2022

Work in progress | 31% Completed

pipe laying work is progressing on .100 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.

Cheruvathur AE
Date: 22/05/2022

Work in progress | 30% Completed

pipe laying work is progressing on .100 nos FHTC is physically done,geo tagging is pending due to disturbed water supply in connection with the road widening work.

Cheruvathur AE
Date: 18/05/2022

Work in progress | 23% Completed

WORK IN PROGRESS

Cheruvathur AE
Date: 10/05/2022

Work in progress | 23% Completed

WORK IN PROGRESS

Cheruvathur AE
Date: 04/05/2022

Work in progress | 21% Completed

WORK IN PROGRESS

Cheruvathur AE
Date: 30/04/2022

Work in progress | 20% Completed

90mm PVC pipe supplied .work in progress

Cheruvathur AE
Date: 20/04/2022

Work in progress | 17% Completed

Due to not supply the PVC pipes work is held up.

Cheruvathur AE
Date: 12/04/2022

Work in progress | 17% Completed

Due to not supply the PVC pipes work is held up.

Cheruvathur AE
Date: 04/04/2022

Work in progress | 17% Completed

Due to not supply the PVC pipes work is held up.

Cheruvathur AE
Date: 01/04/2022

Work in progress | 17% Completed

Due to not supply the PVC pipes work is held up.

Cheruvathur AE
Date: 28/03/2022

Work in progress | 17% Completed

Due to not supply the PVC pipes work is held up.

Cheruvathur AE
Date: 22/03/2022

Work in progress | 17% Completed

Due to not supply the PVC pipes work is held up.

Cheruvathur AE
Date: 13/03/2022

Work in progress | 17% Completed

Due to not supply the PVC pipes work is held up.

Cheruvathur AE
Date: 12/03/2022

Work in progress | 17% Completed

PVC pipe is not supplied,earth work excavation progressing

Cheruvathur AE
Date: 08/03/2022

Work in progress | 16% Completed

PVC pipe is not supplied,earth work excavation progressing

Cheruvathur AE
Date: 04/03/2022

Work in progress | 16% Completed

PVC pipe is not supplied,earth work excavation progressing

Cheruvathur AE
Date: 28/02/2022

Work in progress | 15% Completed

PVC pipe is not supplied,earth work excavation progressing

Cheruvathur AE
Date: 21/02/2022

Work in progress | 10% Completed

PVC pipe is not supplied,earth work excavation progressing

Attached images

img

Cheruvathur AE
Date: 15/02/2022

Work in progress | 2% Completed

PVC pipe is not supplied

Cheruvathur AE
Date: 14/02/2022

Work in progress | 2% Completed

PVC pipe is not supplied

Cheruvathur AE
Date: 10/02/2022

Work in progress | 2% Completed

PVC pipe is not supplied

Cheruvathur AE
Date: 03/02/2022

Work in progress | 2% Completed

PVC pipe is not supplied

Cheruvathur AE
Date: 01/02/2022

Work in progress | 2% Completed

PVC pipe is not supplied