Project | Jal Jeevan Mission-Kasaragod District-West Eleri Panchayath-WSS to West Eleri-Phase II-Laying distribution system and providing FHTC in Kunnumkai - Chittarikkal road area |
---|---|
Project Code | KGDJJM08202965P3 |
Type | Package |
Main Project | Jal Jeevan Mission- Kasaragod District- West Eleri Panchayath- WSS to West Eleri Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission-Kasaragod District-West Eleri Panchayath-WSS to West Eleri-Phase II-Laying distribution system and providing FHTC in Kunnumkai and Chittarikkal road area |
Status | On-going |
District | Kasaragod |
Executing Office | Cheruvathoor Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9980000 |
TS Number | 15230/2021-2022 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 09 Aug 2022 |
Expected date of Completion | 30/09/2022 |
TS Date | 13 Dec 2021 |
---|---|
Estimate Approval | 13 Dec 2021 |
Tender Closing | 24 Dec 2021 |
Price bid opening | 28 Dec 2021 |
Workorder Date | 28 Dec 2021 |
---|---|
NA | 10 Feb 2022 |
Cheruvathur AE |
Date: 02/02/2023 |
Work has been completed | 100% Completed
work completed final bill submitted.
Cheruvathur AE |
Date: 11/11/2022 |
Work has been completed | 100% Completed
Work completed.