Valakom PH Sn AE
Date: 04/08/2023

Work has been completed | 100% Completed

90 mm dia 10 kg /cm2 pvc pipe 7.52 km completed. 160mm dia 10kg/cm2 pvc pipe 6.9 km completed

Valakom PH Sn AE
Date: 01/08/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 29/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 27/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 25/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 22/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 19/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 15/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 13/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 11/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 07/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 05/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 03/07/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 30/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img img img

Valakom PH Sn AE
Date: 27/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 24/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 22/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 19/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 15/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 12/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 09/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 08/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 05/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img img img

Valakom PH Sn AE
Date: 02/06/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img img

Valakom PH Sn AE
Date: 30/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img img img

Valakom PH Sn AE
Date: 27/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img img

Valakom PH Sn AE
Date: 24/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 22/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img img img img

Valakom PH Sn AE
Date: 20/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img

Valakom PH Sn AE
Date: 17/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img img

Valakom PH Sn AE
Date: 15/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 11/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img

Valakom PH Sn AE
Date: 08/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 05/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 02/05/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img

Valakom PH Sn AE
Date: 29/04/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img img

Valakom PH Sn AE
Date: 27/04/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img

Valakom PH Sn AE
Date: 24/04/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img

Valakom PH Sn AE
Date: 20/04/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 17/04/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 13/04/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img

Valakom PH Sn AE
Date: 11/04/2023

Work in progress | 72% Completed

10km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 09/04/2023

Work in progress | 72% Completed

10km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 05/04/2023

Work in progress | 72% Completed

10km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 03/04/2023

Work in progress | 72% Completed

10km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Valakom PH Sn AE
Date: 30/03/2023

Work in progress | 71% Completed

9km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress

Attached images

img

Valakom PH Sn AE
Date: 27/03/2023

Work in progress | 70% Completed

work in progress

Attached images

img

Valakom PH Sn AE
Date: 23/03/2023

Work in progress | 70% Completed

work in progress

Attached images

img img

Valakom PH Sn AE
Date: 20/03/2023

Work in progress | 65% Completed

Work in progress

Valakom PH Sn AE
Date: 17/03/2023

Work in progress | 65% Completed

Work in progress

Valakom PH Sn AE
Date: 13/03/2023

Work in progress | 65% Completed

Work in progress

Valakom PH Sn AE
Date: 10/03/2023

Work in progress | 63% Completed

Work in progress

Valakom PH Sn AE
Date: 06/03/2023

Work in progress | 63% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 03/03/2023

Work in progress | 61% Completed

Work in progress

Valakom PH Sn AE
Date: 28/02/2023

Work in progress | 61% Completed

Work in progress

Valakom PH Sn AE
Date: 24/02/2023

Work in progress | 61% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 22/02/2023

Work in progress | 61% Completed

Work in progress

Valakom PH Sn AE
Date: 20/02/2023

Work in progress | 61% Completed

Work in progress

Valakom PH Sn AE
Date: 17/02/2023

Work in progress | 60% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 14/02/2023

Work in progress | 60% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 10/02/2023

Work in progress | 59% Completed

Work in progress

Attached images

img img

Valakom PH Sn AE
Date: 07/02/2023

Work in progress | 59% Completed

Work in progress

Attached images

img img

Valakom PH Sn AE
Date: 06/02/2023

Work in progress | 59% Completed

Work in progress

Valakom PH Sn AE
Date: 03/02/2023

Work in progress | 58% Completed

Work in progress

Valakom PH Sn AE
Date: 31/01/2023

Work in progress | 58% Completed

Work in progress

Valakom PH Sn AE
Date: 28/01/2023

Work in progress | 58% Completed

Work in progress

Valakom PH Sn AE
Date: 27/01/2023

Work in progress | 58% Completed

Work in progress

Valakom PH Sn AE
Date: 24/01/2023

Work in progress | 58% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 19/01/2023

Work in progress | 57% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 16/01/2023

Work in progress | 56% Completed

Work in progress

Valakom PH Sn AE
Date: 12/01/2023

Work in progress | 54% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 09/01/2023

Work in progress | 54% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 06/01/2023

Work in progress | 54% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 03/01/2023

Work in progress | 53% Completed

work in progress

Attached images

img img img

Valakom PH Sn AE
Date: 31/12/2022

Work in progress | 53% Completed

work in progress

Valakom PH Sn AE
Date: 28/12/2022

Work in progress | 52% Completed

Work in progress

Valakom PH Sn AE
Date: 26/12/2022

Work in progress | 52% Completed

Work in progress

Valakom PH Sn AE
Date: 23/12/2022

Work in progress | 51% Completed

Work in progress

Attached images

img img

Valakom PH Sn AE
Date: 21/12/2022

Work in progress | 51% Completed

Work in progress

Valakom PH Sn AE
Date: 19/12/2022

Work in progress | 51% Completed

Work in progress

Valakom PH Sn AE
Date: 16/12/2022

Work in progress | 51% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 14/12/2022

Work in progress | 51% Completed

Work in progress

Valakom PH Sn AE
Date: 12/12/2022

Work in progress | 50% Completed

Work in progress

Valakom PH Sn AE
Date: 09/12/2022

Work in progress | 50% Completed

Work in progress

Valakom PH Sn AE
Date: 08/12/2022

Work in progress | 50% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 05/12/2022

Work in progress | 50% Completed

Work in progress

Attached images

img

Valakom PH Sn AE
Date: 01/12/2022

Work in progress | 30% Completed

work in progress

Valakom PH Sn AE
Date: 29/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 26/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 23/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 21/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 19/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 17/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 14/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 11/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 09/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 07/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 04/11/2022

Work in progress | 30% Completed

Work in progress

Valakom PH Sn AE
Date: 02/11/2022

Work in progress | 30% Completed

Work in Progress

Valakom PH Sn AE
Date: 01/11/2022

Work in progress | 25% Completed

Work in progress

Valakom PH Sn AE
Date: 31/10/2022

Work in progress | 25% Completed

work in progress

Valakom PH Sn AE
Date: 28/10/2022

Work in progress | 25% Completed

Work in progress

Valakom PH Sn AE
Date: 25/10/2022

Work in progress | 25% Completed

work in progress

Valakom PH Sn AE
Date: 21/10/2022

Work in progress | 25% Completed

work in progress

Valakom PH Sn AE
Date: 20/10/2022

Work in progress | 25% Completed

work in progress

Valakom PH Sn AE
Date: 18/10/2022

Work in progress | 25% Completed

work in progress

Valakom PH Sn AE
Date: 17/10/2022

Work in progress | 25% Completed

work in progress

Valakom PH Sn AE
Date: 15/10/2022

Work in progress | 25% Completed

work in progress

Valakom PH Sn AE
Date: 12/10/2022

Work in progress | 25% Completed

work in progress.

Valakom PH Sn AE
Date: 17/09/2022

Work in progress | 25% Completed

work in progress.

Valakom PH Sn AE
Date: 12/09/2022

Work in progress | 25% Completed

work in progress

Valakom PH Sn AE
Date: 02/09/2022

Work in progress | 25% Completed

1600 m. 160 mm PVC pipe and 90 mm pvc pipe laying completed. work in progress

Valakom PH Sn AE
Date: 30/08/2022

Work in progress | 25% Completed

1600 m , 160 mm PVC , 90 m pipe laying work completed. work in progress

Valakom PH Sn AE
Date: 29/08/2022

Work in progress | 25% Completed

Pipe laying . Work in progress

Valakom Sub Dn AEE
Date: 27/08/2022

Work in progress | 25% Completed

Work in progress