Deposit work : KRFB Improvemets to Ayur Anchal road- Laying pipe line on both sides of Ayur Anchal Punalur road

Project Deposit work : KRFB Improvemets to Ayur Anchal road- Laying pipe line on both sides of Ayur Anchal Punalur road
Project Code KLMDEPO032212068P1
Type Package
Main Project Deposit work : KRFB Improvemets to Ayur Anchal Punalur road- Laying pipe line on both sides of Ayur Anchal Punalur road
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Laying pipe line both sides of Ayur Anchal road in connection with road improvement work
Status Completed
District Kollam
Executing Office Valakom PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 25880000
TS Number 850/2022-23
Technical specification Laying of pipe line on both sides of road in connection with road improvement work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/06/2022
Scheduled date of Completion as per agreement 30 Nov 2022
Expected date of Completion 01/08/2023

Processing Dates

TS Date 13 Apr 2022
Estimate Approval 13 Apr 2022
NIT Approval 15 Apr 2022
Tender Closing 03 May 2022
Technichal Pre-Qualification 03 May 2022
Price bid opening 05 May 2022

Approval Dates

Workorder Date 16 May 2022
NA 01 Jun 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Valakom PH Sn AE
Date: 04/08/2023

Work has been completed | 100% Completed

90 mm dia 10 kg /cm2 pvc pipe 7.52 km completed. 160mm dia 10kg/cm2 pvc pipe 6.9 km completed.

Valakom PH Sn AE
Date: 01/08/2023

Work in progress | 73% Completed

12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress.