| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 25/06/2025 |
Work in progress | 66% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 19/06/2025 |
Work in progress | 65% Completed
ongoing
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 30/01/2025 |
Work in progress | 31% Completed
ongoing
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 07/12/2024 |
Work in progress | 24% Completed
ONGOING
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 03/12/2024 |
Work in progress | 20% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 14/11/2024 |
Work in progress | 7% Completed
on going
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 06/11/2024 |
Work has started | 0% Completed
not started
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 26/10/2024 |
Work has started | 0% Completed
not started
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 23/10/2024 |
Work has started | 0% Completed
Not started
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 05/10/2024 |
Work has started | 0% Completed
NOT STARTED
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 24/09/2024 |
Work has started | 0% Completed
not started
| Kozhikode WestHill Distribution Sn - 1/1 - AE |
| Date: 21/08/2024 |
Work has started | 0% Completed
WORK NOT STARTED
| Kozhikode PH Dn EE |
| Date: 21/04/2024 |
Work in progress | 23% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 21% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 18% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 15% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 10% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 12/01/2024 |
Work in progress | 7% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 12/12/2023 |
Work in progress | 6% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 29/11/2023 |
Work in progress | 5% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 31/10/2023 |
Work has started | 0% Completed
Agreement Executed