Konni PH Sn - AE
Date: 26/06/2024

Work in progress | 92% Completed

FHTC- 1686, Pipe laid 90mm to 160 mm PVC- 67.844 km 80mm to 150 mm GI -3.99 150 mm to 300 mm DI -2.9 km

Konni PH Sn - AE
Date: 24/06/2024

Work in progress | 92% Completed

FHTC- 1671, Pipe laid 90mm to 160 mm PVC- 67.844 km 80mm to 150 mm GI -3.99 150 mm to 300 mm DI -2.9 km

Konni PH Sn - AE
Date: 16/05/2024

Work in progress | 86% Completed

FHTC- 1389, Pipe laid 90mm to 160 mm PVC- 66.44 km 80mm to 150 mm GI -3.99 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 23/04/2024

Work in progress | 85% Completed

FHTC- 1256, Pipe laid 90mm to 160 mm PVC- 66.44 km 80mm to 150 mm GI -3.99 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 08/04/2024

Work in progress | 84% Completed

FHTC- 1035, Pipe laid 90mm to 160 mm PVC- 66.44 km 80mm to 150 mm GI -3.99 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 21/03/2024

Work in progress | 80% Completed

FHTC- 1035, Pipe laid 90mm to 160 mm PVC- 58.319 km 80mm to 150 mm GI -3.630 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 11/03/2024

Work in progress | 80% Completed

FHTC- 1035, Pipe laid 90mm to 160 mm PVC- 58.319 km 80mm to 150 mm GI -3.630 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 07/03/2024

Work in progress | 80% Completed

FHTC- 1035, Pipe laid 90mm to 160 mm PVC- 58.319 km 80mm to 150 mm GI -3.630 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 22/02/2024

Work in progress | 80% Completed

FHTC- 1025, Pipe laid 90mm to 160 mm PVC- 58.319 km 80mm to 150 mm GI -3.630 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 13/02/2024

Work in progress | 80% Completed

FHTC- 1025, Pipe laid 90mm to 160 mm PVC- 60.12 km 80mm to 150 mm GI -3.630 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 06/02/2024

Work in progress | 76% Completed

FHTC- 994 Pipe laid 90mm to 160 mm PVC- 58.319 km 80mm to 150 mm GI -3.630 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 29/01/2024

Work in progress | 76% Completed

FHTC- 979 Pipe laid 90mm to 160 mm PVC- 58.319 km 80mm to 150 mm GI -3.630 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 21/01/2024

Work in progress | 76% Completed

FHTC- 979 Pipe laid 90mm to 160 mm PVC- 58.319 km 80mm to 150 mm GI -3.630 150 mm to 300 mm DI -2.895 km

Konni PH Sn - AE
Date: 20/01/2024

Work in progress | 1% Completed

Agreement Executed on 17.03.2023

Konni PH Sn - AE
Date: 12/01/2024

Work in progress | 1% Completed

Agreement Executed on 17.03.2023

Konni PH Sn - AE
Date: 06/01/2024

Work in progress | 1% Completed

Agreement Executed on 17.03.2023

Pathanamthitta PH Dn EE
Date: 17/03/2023

Work in progress | 1% Completed

Agreement Executed on 17.03.2023