Jal Jeevan Mission (JJM)-5th SWSM: Providing Distribution System and FHTCs in Konni Panchayath.-Supplying and laying distribution lines and providing 3660FHTCs in Konni pt:-General Civil Work

Project Jal Jeevan Mission (JJM)-5th SWSM: Providing Distribution System and FHTCs in Konni Panchayath.-Supplying and laying distribution lines and providing 3660FHTCs in Konni pt:-General Civil Work
Project Code PTAJJM052214968P1
Type Package
Main Project Jal Jeevan Mission (JJM)-5th SWSM: Providing Distribution System and FHTCs in Konni Panchayath.-Supplying and laying distribution lines and providing 3660FHTCs in Konni pt:-General Civil Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-5th SWSM: Providing Distribution System and FHTCs in Konni Panchayath.-Supplying and laying distribution lines and providing 3660FHTCs in Konni pt:-General Civil Work
Status On-going
District Pathanamthitta
Executing Office Konni Sn
Agreement Number
Agreement Date
TS Amount (Rs) 196800000
TS Number TS/13167/2022_5_1_1
Technical specification Supplying and laying distribution lines and providing 3660FHTCs in Konni pt

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/03/2023
Scheduled date of Completion as per agreement 17 Dec 2024
Expected date of Completion Date is not specified

Processing Dates

TS Date 17 Dec 2022
Estimate Approval 17 Dec 2022

Approval Dates

NA 17 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Konni PH Sn - AE
Date: 26/06/2024

Work in progress | 92% Completed

FHTC- 1686, Pipe laid 90mm to 160 mm PVC- 67.844 km 80mm to 150 mm GI -3.99 150 mm to 300 mm DI -2.9 km.

Konni PH Sn - AE
Date: 24/06/2024

Work in progress | 92% Completed

FHTC- 1671, Pipe laid 90mm to 160 mm PVC- 67.844 km 80mm to 150 mm GI -3.99 150 mm to 300 mm DI -2.9 km.