Nedumkandam Sn AE
Date: 09/05/2022

Work has been completed | 100% Completed

Flow meter supplied and fitted. Mobile phone not supplied. But it is not a mandatory work.

Attached images

img img

Nedumkandam Sn AE
Date: 05/05/2022

Work in progress | 99% Completed

Flowmeter supplied

Nedumkandam Sn AE
Date: 28/04/2022

Work in progress | 97% Completed

Flowmeter is not installed till date. Mobile phone not supplied.

Nedumkandam Sn AE
Date: 18/04/2022

Work in progress | 97% Completed

Flowmeter is not installed till date. Mobile phone not supplied.

Nedumkandam Sn AE
Date: 12/04/2022

Work in progress | 97% Completed

Flowmeter is not installed till date. Mobile phone not supplied.

Nedumkandam Sn AE
Date: 05/04/2022

Work in progress | 97% Completed

Flowmeter is not installed till date. Mobile phone not supplied.

Nedumkandam Sn AE
Date: 29/03/2022

Work in progress | 97% Completed

Flowmeter is not installed till date. Mobile phone not supplied.

Nedumkandam Sn AE
Date: 25/03/2022

Work in progress | 97% Completed

Flowmeter is not installed till date. Mobile phone not supplied.

Nedumkandam Sn AE
Date: 24/03/2022

Work in progress | 97% Completed

Flowmeter installation pending

Nedumkandam Sn AE
Date: 17/03/2022

Work in progress | 97% Completed

Flowmeter installation pending

Nedumkandam Sn AE
Date: 10/03/2022

Work in progress | 97% Completed

Flowmeter installation pending

Nedumkandam Sn AE
Date: 03/03/2022

Work in progress | 97% Completed

Flowmeter installation pending

Nedumkandam Sn AE
Date: 25/02/2022

Work in progress | 97% Completed

Flowmeter installation pending

Nedumkandam Sn AE
Date: 21/02/2022

Work in progress | 97% Completed

Flowmeter installation pending

Nedumkandam Sn AE
Date: 15/02/2022

Work in progress | 97% Completed

Pipe laying and testing completed

Nedumkandam Sn AE
Date: 10/02/2022

Work in progress | 97% Completed

Pipe laying and testing completed

Nedumkandam Sn AE
Date: 04/02/2022

Work in progress | 97% Completed

Pipe laying and testing completed

Nedumkandam Sn AE
Date: 31/01/2022

Work in progress | 97% Completed

Pipe laying and testing completed

Nedumkandam Sn AE
Date: 23/01/2022

Work in progress | 97% Completed

Pipe laying and testing completed

Nedumkandam Sn AE
Date: 18/01/2022

Work in progress | 85% Completed

Work in progress

Nedumkandam Sn AE
Date: 11/01/2022

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 04/01/2022

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 31/12/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 29/12/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 24/12/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 20/12/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 12/12/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 06/12/2021

Work in progress | 82% Completed

Work in Progress

Nedumkandam Sn AE
Date: 28/11/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 17/11/2021

Work in progress | 82% Completed

Work in progress. Pipe laying work delayed due to monsoon effects

Nedumkandam Sn AE
Date: 15/11/2021

Work in progress | 82% Completed

Work in progress. Pipe laying work delayed due to monsoon effects

Nedumkandam Sn AE
Date: 09/11/2021

Work in progress | 82% Completed

Work in progress. Pipe laying work delayed due to monsoon effects

Nedumkandam Sn AE
Date: 05/11/2021

Work in progress | 82% Completed

Work in progress. Pipe laying work delayed due to monsoon effects

Nedumkandam Sn AE
Date: 01/11/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 21/10/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 12/10/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 07/10/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 30/09/2021

Work in progress | 82% Completed

Work in progress

Thodupuzha PH Dn EE
Date: 29/09/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 25/09/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 20/09/2021

Work in progress | 82% Completed

Work in progress

Thodupuzha PH Dn EE
Date: 16/09/2021

Work in progress | 82% Completed

Work in progress

Nedumkandam Sn AE
Date: 06/09/2021

Work in progress | 82% Completed

Work in progress

Thodupuzha PH Dn EE
Date: 31/08/2021

Work in progress | 82% Completed

Work in progress

Thodupuzha PH Dn EE
Date: 23/08/2021

Work in progress | 82% Completed

Work in progress

Thodupuzha PH Dn EE
Date: 17/08/2021

Work in progress | 82% Completed

Work in progress

Thodupuzha PH Dn EE
Date: 10/08/2021

Work in progress | 82% Completed

Work in progress

Attached images

img

Thodupuzha PH Dn EE
Date: 04/08/2021

Work in progress | 81% Completed

Work in progress

Thodupuzha PH Dn EE
Date: 27/07/2021

Work in progress | 81% Completed

Work in progress

Thodupuzha PH Dn EE
Date: 20/07/2021

Work in progress | 81% Completed

Work in progress

Thodupuzha PH Dn EE
Date: 11/07/2021

Work in progress | 81% Completed

Installation completed

Nedumkandam Sn AE
Date: 01/07/2021

Work in progress | 80% Completed

Pump and motor installed

Attached images

img img img img

Thodupuzha PH Dn EE
Date: 28/06/2021

Work in progress | 25% Completed

Work in progress

Nedumkandam Sn AE
Date: 28/05/2021

Work in progress | 25% Completed

Overhauling of One pump work is completed

Attached images

img

Nedumkandam Sn AE
Date: 10/03/2021

Work in progress | 10% Completed

Overhauling of One pump work is ongoing