| Nedumkandam Sn AE |
| Date: 09/05/2022 |
| Nedumkandam Sn AE |
| Date: 05/05/2022 |
Work in progress | 99% Completed
Flowmeter supplied
| Nedumkandam Sn AE |
| Date: 28/04/2022 |
Work in progress | 97% Completed
Flowmeter is not installed till date. Mobile phone not supplied.
| Nedumkandam Sn AE |
| Date: 18/04/2022 |
Work in progress | 97% Completed
Flowmeter is not installed till date. Mobile phone not supplied.
| Nedumkandam Sn AE |
| Date: 12/04/2022 |
Work in progress | 97% Completed
Flowmeter is not installed till date. Mobile phone not supplied.
| Nedumkandam Sn AE |
| Date: 05/04/2022 |
Work in progress | 97% Completed
Flowmeter is not installed till date. Mobile phone not supplied.
| Nedumkandam Sn AE |
| Date: 29/03/2022 |
Work in progress | 97% Completed
Flowmeter is not installed till date. Mobile phone not supplied.
| Nedumkandam Sn AE |
| Date: 25/03/2022 |
Work in progress | 97% Completed
Flowmeter is not installed till date. Mobile phone not supplied.
| Nedumkandam Sn AE |
| Date: 24/03/2022 |
Work in progress | 97% Completed
Flowmeter installation pending
| Nedumkandam Sn AE |
| Date: 17/03/2022 |
Work in progress | 97% Completed
Flowmeter installation pending
| Nedumkandam Sn AE |
| Date: 10/03/2022 |
Work in progress | 97% Completed
Flowmeter installation pending
| Nedumkandam Sn AE |
| Date: 03/03/2022 |
Work in progress | 97% Completed
Flowmeter installation pending
| Nedumkandam Sn AE |
| Date: 25/02/2022 |
Work in progress | 97% Completed
Flowmeter installation pending
| Nedumkandam Sn AE |
| Date: 21/02/2022 |
Work in progress | 97% Completed
Flowmeter installation pending
| Nedumkandam Sn AE |
| Date: 15/02/2022 |
Work in progress | 97% Completed
Pipe laying and testing completed
| Nedumkandam Sn AE |
| Date: 10/02/2022 |
Work in progress | 97% Completed
Pipe laying and testing completed
| Nedumkandam Sn AE |
| Date: 04/02/2022 |
Work in progress | 97% Completed
Pipe laying and testing completed
| Nedumkandam Sn AE |
| Date: 31/01/2022 |
Work in progress | 97% Completed
Pipe laying and testing completed
| Nedumkandam Sn AE |
| Date: 23/01/2022 |
Work in progress | 97% Completed
Pipe laying and testing completed
| Nedumkandam Sn AE |
| Date: 18/01/2022 |
Work in progress | 85% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 11/01/2022 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 04/01/2022 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 31/12/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 29/12/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 24/12/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 20/12/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 12/12/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 06/12/2021 |
Work in progress | 82% Completed
Work in Progress
| Nedumkandam Sn AE |
| Date: 28/11/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 17/11/2021 |
Work in progress | 82% Completed
Work in progress. Pipe laying work delayed due to monsoon effects
| Nedumkandam Sn AE |
| Date: 15/11/2021 |
Work in progress | 82% Completed
Work in progress. Pipe laying work delayed due to monsoon effects
| Nedumkandam Sn AE |
| Date: 09/11/2021 |
Work in progress | 82% Completed
Work in progress. Pipe laying work delayed due to monsoon effects
| Nedumkandam Sn AE |
| Date: 05/11/2021 |
Work in progress | 82% Completed
Work in progress. Pipe laying work delayed due to monsoon effects
| Nedumkandam Sn AE |
| Date: 01/11/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 21/10/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 12/10/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 07/10/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 30/09/2021 |
Work in progress | 82% Completed
Work in progress
| Thodupuzha PH Dn EE |
| Date: 29/09/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 25/09/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 20/09/2021 |
Work in progress | 82% Completed
Work in progress
| Thodupuzha PH Dn EE |
| Date: 16/09/2021 |
Work in progress | 82% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 06/09/2021 |
Work in progress | 82% Completed
Work in progress
| Thodupuzha PH Dn EE |
| Date: 31/08/2021 |
Work in progress | 82% Completed
Work in progress
| Thodupuzha PH Dn EE |
| Date: 23/08/2021 |
Work in progress | 82% Completed
Work in progress
| Thodupuzha PH Dn EE |
| Date: 17/08/2021 |
Work in progress | 82% Completed
Work in progress
| Thodupuzha PH Dn EE |
| Date: 10/08/2021 |
| Thodupuzha PH Dn EE |
| Date: 04/08/2021 |
Work in progress | 81% Completed
Work in progress
| Thodupuzha PH Dn EE |
| Date: 27/07/2021 |
Work in progress | 81% Completed
Work in progress
| Thodupuzha PH Dn EE |
| Date: 20/07/2021 |
Work in progress | 81% Completed
Work in progress
| Thodupuzha PH Dn EE |
| Date: 11/07/2021 |
Work in progress | 81% Completed
Installation completed
| Nedumkandam Sn AE |
| Date: 01/07/2021 |
| Thodupuzha PH Dn EE |
| Date: 28/06/2021 |
Work in progress | 25% Completed
Work in progress
| Nedumkandam Sn AE |
| Date: 28/05/2021 |
| Nedumkandam Sn AE |
| Date: 10/03/2021 |
Work in progress | 10% Completed
Overhauling of One pump work is ongoing