Optimisation of Production and Transmission- (Energy Conservation) RWSS to Merykulam-Suppl and erection of 1 nos 25 HP openwell submersible standby pumpset

Project Optimisation of Production and Transmission- (Energy Conservation) RWSS to Merykulam-Suppl and erection of 1 nos 25 HP openwell submersible standby pumpset
Project Code IDKGOK10205919P1
Type Package
Main Project Optimisation of Production and Transmission- (Energy Conservation) RWSS to Marykulam-Suppl and erection of 2 nos 25 HP openwell submersible standby pumpset
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description Optimisation of Production and Transmission- (Energy Conservation) RWSS to Merykulam-Suppl and erection of 2 nos 25 HP openwell submersible standby pumpset
Status On-going
District Idukki
Executing Office Peerumedu Sn
Agreement Number
Agreement Date
TS Amount (Rs) 700000
TS Number
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/02/2021
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 28/02/2022

Processing Dates

TS Date 10 Dec 2020
Estimate Approval 10 Dec 2020
Tender Closing 20 Feb 2021

Approval Dates

Workorder Date 20 Feb 2021
NA 20 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nedumkandam Sn AE
Date: 09/05/2022

Work has been completed | 100% Completed

Flow meter supplied and fitted. Mobile phone not supplied. But it is not a mandatory work..

Attached images

img img

Nedumkandam Sn AE
Date: 05/05/2022

Work in progress | 99% Completed

Flowmeter supplied.