| Pathanapuram WS Sn - AE |
| Date: 28/09/2026 |
Work in progress | 80% Completed
GI Pumping line cutting, welding work ongoing
| Pathanapuram WS Sn - AE |
| Date: 21/09/2026 |
Work in progress | 75% Completed
GI laying started for Pumping main
| Pathanapuram WS Sn - AE |
| Date: 14/09/2026 |
Work in progress | 71% Completed
GI laying started for Pumping main
| Pathanapuram WS Sn - AE |
| Date: 10/09/2026 |
Work in progress | 70% Completed
pvc laying work completed
| Pathanapuram WS Sn - AE |
| Date: 02/09/2026 |
Work in progress | 69% Completed
pvc laying work ongoing
| Pathanapuram WS Sn - AE |
| Date: 26/08/2026 |
Work in progress | 68% Completed
pvc laying work ongoing
| Pathanapuram WS Sn - AE |
| Date: 12/08/2026 |
Work in progress | 65% Completed
pvc laying work ongoing
| Pathanapuram WS Sn - AE |
| Date: 31/07/2026 |
Work in progress | 60% Completed
pvc laying work started
| Pathanapuram WS Sn - AE |
| Date: 20/06/2026 |
Work in progress | 55% Completed
no work
| Pathanapuram WS Sn - AE |
| Date: 10/06/2026 |
Work in progress | 45% Completed
GI laying work completed
| Pathanapuram WS Sn - AE |
| Date: 30/05/2026 |
Work in progress | 35% Completed
GI Cutting, Welding work ongoing
| Pathanapuram WS Sn - AE |
| Date: 18/05/2026 |
Work in progress | 25% Completed
GI laying work ongoing
| Pathanapuram WS Sn - AE |
| Date: 11/05/2026 |
Work in progress | 15% Completed
GI laying work ongoing
| Pathanapuram WS Sn - AE |
| Date: 05/05/2026 |
Work in progress | 10% Completed
GI laying work ongoing
| Pathanapuram WS Sn - AE |
| Date: 29/04/2026 |
Work in progress | 5% Completed
GI laying work ongoing
| Pathanapuram WS Sn - AE |
| Date: 22/04/2026 |
Work in progress | 1% Completed
GI laying work started