| Project | DEPOSIT-Kollam Jilla Panchayath - WSS to Karyara & Myladumpara |
|---|---|
| Project Code | KLMGOK082518328P1 |
| Type | Package |
| Main Project | DEPOSIT-Kollam Jilla Panchayath - WSS to Karyara & Myladumpara |
| Funding Agency | GOK |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | DEPOSIT-Kollam Jilla Panchayath - WSS to Karyara & Myladumpara-SUPPLY AND INSTALLATION OF INLINE BOOSTER PUMP AT MYLADUMPARA & 100 MM PUMPING MAIN IN VILAKKUDY PANCHAYATH-Pipeline Work |
| Status | On-going |
| District | Kollam |
| Executing Office | Pathanapuram WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 4990000 |
| TS Number | TS/866/2025_26_1_1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 26/12/2025 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 25/09/2026 |
| TS Date | 18 Sep 2025 |
|---|---|
| Estimate Approval | 07 Aug 2025 |
| Pathanapuram WS Sn - AE |
| Date: 28/09/2026 |
Work in progress | 80% Completed
GI Pumping line cutting, welding work ongoing.
| Pathanapuram WS Sn - AE |
| Date: 21/09/2026 |
Work in progress | 75% Completed
GI laying started for Pumping main.