| Thodupuzha PH Sub Dn AEE |
| Date: 30/12/2025 |
Work has been completed | 100% Completed
Work completed
| Thodupuzha PH Sn |
| Date: 22/12/2025 |
Work in progress | 75% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted
| Thodupuzha PH Sn |
| Date: 29/08/2025 |
Work in progress | 75% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted
| Thodupuzha PH Sn |
| Date: 27/08/2025 |
Work in progress | 75% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted
| Thodupuzha PH Sn |
| Date: 11/08/2025 |
Work in progress | 75% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted
| Thodupuzha PH Sn |
| Date: 04/08/2025 |
Work in progress | 75% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted
| Thodupuzha PH Sn |
| Date: 02/08/2025 |
Work in progress | 75% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted
| Thodupuzha PH Sn |
| Date: 30/07/2025 |
Work in progress | 75% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted
| Thodupuzha PH Sn |
| Date: 23/07/2025 |
Work in progress | 75% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted
| Thodupuzha PH Sn |
| Date: 07/07/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given
| Thodupuzha PH Sn |
| Date: 21/06/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given
| Thodupuzha PH Sn |
| Date: 17/06/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given
| Thodupuzha PH Sn |
| Date: 22/04/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 19/04/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 07/04/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 27/03/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 24/03/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 17/03/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 06/03/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 17/02/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 01/02/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 24/01/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 22/01/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 13/01/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 10/01/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 03/01/2025 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 26/12/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 18/12/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 13/12/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 09/12/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 06/12/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 02/12/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 29/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 25/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 21/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 18/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 16/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 13/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 11/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 257 FHTC Given
| Thodupuzha PH Sn |
| Date: 08/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 227 FHTC Given
| Thodupuzha PH Sn |
| Date: 06/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 227 FHTC Given
| Thodupuzha PH Sn |
| Date: 04/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 227 FHTC Given
| Thodupuzha PH Sn |
| Date: 01/11/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 227 FHTC Given
| Thodupuzha PH Sn |
| Date: 26/10/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 227 FHTC Given
| Thodupuzha PH Sn |
| Date: 21/10/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 227 FHTC Given
| Thodupuzha PH Sn |
| Date: 18/10/2024 |
Work in progress | 50% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 227 FHTC Given.
| Thodupuzha PH Sn |
| Date: 17/10/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 16/10/2024 |
Work has started | 0% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 15/10/2024 |
Work has been completed | 100% Completed
duplication of package-2
| Thodupuzha PH Sn |
| Date: 04/10/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Dn EE |
| Date: 02/10/2024 |
Work in progress | 41% Completed
work in progress
| Thodupuzha PH Sn |
| Date: 11/09/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 03/09/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 19/08/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 14/08/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 12/08/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 02/08/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 29/07/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 24/07/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 15/07/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 08/07/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 05/07/2024 |
Work in progress | 41% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 03/07/2024 |
Work in progress | 40% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 01/07/2024 |
Work in progress | 40% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 28/06/2024 |
Work in progress | 40% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 26/06/2024 |
Work in progress | 40% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 21/06/2024 |
Work in progress | 40% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 18/06/2024 |
Work in progress | 40% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 14/06/2024 |
Work in progress | 40% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 12/06/2024 |
Work in progress | 40% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 07/06/2024 |
Work in progress | 40% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 05/06/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 03/06/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 31/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 29/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 24/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 23/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 20/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 17/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 13/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 08/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 06/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 02/05/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 29/04/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 27/04/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 23/04/2024 |
Work in progress | 31% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 19/04/2024 |
Work in progress | 30% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
| Thodupuzha PH Sn |
| Date: 17/04/2024 |
Work in progress | 30% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied, Distribution Pipeline work started
Attached images
| Thodupuzha PH Sn |
| Date: 15/04/2024 |
Work in progress | 24% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 12/04/2024 |
Work in progress | 24% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 08/04/2024 |
Work in progress | 24% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 05/04/2024 |
Work in progress | 24% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 03/04/2024 |
Work in progress | 24% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 01/04/2024 |
Work in progress | 24% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 29/03/2024 |
Work in progress | 24% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 23/03/2024 |
Work in progress | 23% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 18/03/2024 |
Work in progress | 20% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 15/03/2024 |
Work in progress | 20% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 13/03/2024 |
Work in progress | 20% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 11/03/2024 |
Work in progress | 20% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 06/03/2024 |
Work in progress | 17% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 04/03/2024 |
Work in progress | 17% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 28/02/2024 |
Work in progress | 17% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 26/02/2024 |
Work in progress | 17% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 23/02/2024 |
Work in progress | 17% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 21/02/2024 |
Work in progress | 15% Completed
187 Nos. FHTC given ,63 mm PVC -1000 m laid,63 mm PVC Pipe 2250 m Supplied. 75 mm PVC Pipe 2750 m Supplied.
| Thodupuzha PH Sn |
| Date: 19/02/2024 |
Work in progress | 15% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 15/02/2024 |
Work in progress | 15% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; Tank Putty work in progress ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 07/02/2024 |
Work in progress | 15% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; Tank Putty work in progress ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 23/01/2024 |
Work in progress | 15% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; Tank Putty work in progress ,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 01/01/2024 |
Work in progress | 12% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; 63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Dn EE |
| Date: 18/12/2023 |
Work in progress | 12% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; 63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied.
| Thodupuzha PH Sn |
| Date: 15/12/2023 |
Work in progress | 10% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; PVC Pipes Supplied (75%)
| Thodupuzha PH Dn EE |
| Date: 12/12/2023 |
Work in progress | 10% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed; PVC Pipes Supplied (75%)