| Project | AMRUT 2.0- package 2 -UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality |
|---|---|
| Project Code | IDKAMRUT112213858P2 |
| Type | Package |
| Main Project | AMRUT 2.0 -UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality-General Civil Work |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT 2.0- package 2 -UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality Idikettipara Area |
| Status | On-going |
| District | Idukki |
| Executing Office | Thodupuzha PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 106400000 |
| TS Number | 6877/2023-2024 |
| Technical specification | AMRUT 2.0-Package 2 |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 31/03/2023 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| TS Date | 22 Jun 2022 |
|---|---|
| Estimate Approval | 22 Jun 2023 |
| NIT Approval | 26 Jun 2023 |
| Tender Closing | 07 Oct 2023 |
| Price bid opening | 07 Nov 2023 |
| Thodupuzha PH Sub Dn AEE |
| Date: 30/12/2025 |
Work has been completed | 100% Completed
Work completed.
| Thodupuzha PH Sn |
| Date: 22/12/2025 |
Work in progress | 75% Completed
0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted.