Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT 2.0- package 2 -UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality

Project AMRUT 2.0- package 2 -UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality
Project Code IDKAMRUT112213858P2
Type Package
Main Project AMRUT 2.0 -UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality-General Civil Work
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT 2.0- package 2 -UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality Idikettipara Area
Status On-going
District Idukki
Executing Office Thodupuzha PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 106400000
TS Number 6877/2023-2024
Technical specification AMRUT 2.0-Package 2

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/03/2023
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 22 Jun 2022
Estimate Approval 22 Jun 2023
NIT Approval 26 Jun 2023
Tender Closing 07 Oct 2023
Price bid opening 07 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thodupuzha PH Sub Dn AEE
Date: 30/12/2025

Work has been completed | 100% Completed

Work completed.

Thodupuzha PH Sn
Date: 22/12/2025

Work in progress | 75% Completed

0.5LL Capacity GLSR at Idikettippara - Rock Levelling, Dowel bars completed;Footing Completed ,base slab completed, side wall and Roof slab completed ,plastering completed,63 mm PVC Pipe 1000 m Supplied. 75 mm PVC Pipe 500 m Supplied. 90 mm PVC Pipe 2000 m Supplied,50MM GI Pipe 3700mtr Supplied, 65MM GI Pipe 2000mtr Supplied , 80MM GI Pipe 4250mtr Supplied,pumping line and Distribution Pipeline work started 90mm PVC pipe 1996m laid,63mm PVC pipe 472m laid,50mm GI pipe 1041.4m laid, 65mm GI pipe 317.2m laid,80 GI pipe 836.8m laid Total FHTC 440, 441 FHTC Given, RE Sumitted.