| Madathara PH Sn - AE |
| Date: 09/01/2026 |
Work in progress | 90% Completed
121 FHTC completed. road restoration pending
| Madathara PH Sn - AE |
| Date: 23/09/2025 |
Work in progress | 90% Completed
on going
| Madathara PH Sn - AE |
| Date: 01/09/2025 |
Work in progress | 75% Completed
only road restoration pending
| Madathara PH Sn - AE |
| Date: 07/05/2025 |
Work in progress | 70% Completed
On Going