Jal Jeevan Mission (JJM)-Alayamon Panchayath re appropriation-WARD 10,11,12,13,14-Pipeline Work

Project Jal Jeevan Mission (JJM)-Alayamon Panchayath re appropriation-WARD 10,11,12,13,14-Pipeline Work
Project Code KLMJJM102316952P1
Type Package
Main Project Jal Jeevan Mission (JJM)-Alayamon Panchayath re appropriation-WARD 10,11,12,13,14-Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-Alayamon Panchayath re appropriation-WARD 10,11,12,13,14-Pipeline Work
Status On-going
District Kollam
Executing Office Madathara Sn
Agreement Number
Agreement Date
TS Amount (Rs) 6617700
TS Number WRD/KWA-CE(SR)/EST_TS/3321/2024_26_3_2
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/10/2025

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Madathara PH Sn - AE
Date: 09/01/2026

Work in progress | 90% Completed

121 FHTC completed. road restoration pending.

Madathara PH Sn - AE
Date: 23/09/2025

Work in progress | 90% Completed

on going.