Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Koothuparamba Proj AE 2
Date: 07/06/2024

Work has been completed | 100% Completed

Commissioned on 23/5/2024

Koothuparamba Proj AE 2
Date: 03/06/2024

Work has been completed | 100% Completed

Commissioned on 23/5/2024

Koothuparamba Proj AE 2
Date: 29/05/2024

Work has been completed | 100% Completed

Commissioned on 23/5/2024

Koothuparamba Proj AE 2
Date: 25/05/2024

Work has been completed | 100% Completed

Commissioned on 23/5/2024

Koothuparamba Proj AE 2
Date: 21/05/2024

Work in progress | 99% Completed

Pumpset and transformer commisioning on prgress

Koothuparamba Proj AE 2
Date: 02/05/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection

Koothuparamba Proj AE 2
Date: 18/04/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection

Koothuparamba Proj AE 2
Date: 15/04/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection

Koothuparamba Proj AE 2
Date: 11/04/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection

Koothuparamba Proj AE 2
Date: 05/04/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection

Koothuparamba Proj AE 2
Date: 02/04/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection

Koothuparamba Proj AE 2
Date: 28/03/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection

Koothuparamba Proj AE 2
Date: 21/03/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection.

Koothuparamba Proj AE 2
Date: 19/03/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection.

Koothuparamba Proj AE 2
Date: 14/03/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection.

Koothuparamba Proj AE 2
Date: 11/03/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection.

Koothuparamba Proj AE 2
Date: 07/03/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection.

Koothuparamba Proj AE 2
Date: 04/03/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection.

Koothuparamba Proj AE 2
Date: 29/02/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection.

Koothuparamba Proj AE 2
Date: 25/02/2024

Work in progress | 99% Completed

Demand note recieved from KSEB for power connection.

Koothuparamba Proj AE 2
Date: 14/02/2024

Work in progress | 99% Completed

Waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 05/02/2024

Work in progress | 99% Completed

Waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 30/01/2024

Work in progress | 99% Completed

Waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 23/01/2024

Work in progress | 99% Completed

Waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 17/01/2024

Work in progress | 99% Completed

Waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 01/01/2024

Work in progress | 99% Completed

Waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 12/12/2023

Work in progress | 99% Completed

All the erection work completed and commissioning pending due to delay in getting safety certification from electrical inspectorate

Koothuparamba Proj AE 2
Date: 02/11/2023

Work in progress | 99% Completed

Waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 19/10/2023

Work in progress | 99% Completed

Waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 06/10/2023

Work in progress | 99% Completed

Waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 13/09/2023

Work in progress | 99% Completed

waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 10/08/2023

Work in progress | 99% Completed

waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 03/08/2023

Work in progress | 99% Completed

waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 26/07/2023

Work in progress | 99% Completed

waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 19/07/2023

Work in progress | 99% Completed

waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 11/07/2023

Work in progress | 99% Completed

waiting for KSEB connection

Koothuparamba Proj AE 2
Date: 05/07/2023

Work in progress | 99% Completed

waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 30/06/2023

Work in progress | 99% Completed

waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 23/06/2023

Work in progress | 99% Completed

waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 19/06/2023

Work in progress | 99% Completed

waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 12/06/2023

Work in progress | 97% Completed

waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 06/06/2023

Work in progress | 97% Completed

waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 01/06/2023

Work in progress | 97% Completed

Finishing work on progress, waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 25/05/2023

Work in progress | 97% Completed

Finishing work on progress,waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 22/05/2023

Work in progress | 97% Completed

Finishing work on progress,waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 17/05/2023

Work in progress | 97% Completed

Finishing work on progress,waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 10/05/2023

Work in progress | 96% Completed

Finishing work on progress,waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 08/05/2023

Work in progress | 95% Completed

Finishing work on progress,waiting for safety certification from KSEB

Koothuparamba Proj AE 2
Date: 04/05/2023

Work in progress | 87% Completed

Pump interconnection work ongoing.Fencing work on progress,lighting work on progress

Koothuparamba Proj AE 2
Date: 28/04/2023

Work in progress | 86% Completed

Pump interconnection work ongoing.Fencing work on progress

Koothuparamba Proj AE 2
Date: 24/04/2023

Work in progress | 85% Completed

erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.Fencing work on progress

Koothuparamba Proj AE 2
Date: 18/04/2023

Work in progress | 81% Completed

erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.

Koothuparamba Proj AE 2
Date: 05/04/2023

Work in progress | 80% Completed

erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.

Koothuparamba Proj AE 2
Date: 30/03/2023

Work in progress | 78% Completed

erection of transformer ongaoing , termination work ongoing

Koothuparamba Proj AE 2
Date: 16/03/2023

Work in progress | 75% Completed

Erection of transformer are in progress

Koothuparamba Proj AE 2
Date: 09/03/2023

Work in progress | 70% Completed

Erection of transformer are in progress

Koothuparamba Proj AE 2
Date: 04/03/2023

Work in progress | 68% Completed

Pumpset erection work completed

Koothuparamba Proj AE 2
Date: 02/03/2023

Work in progress | 60% Completed

Erection of transformer and pump sets are in progress

Attached images

img img

Koothuparamba Proj AE 2
Date: 01/03/2023

Work in progress | 55% Completed

Erection of transformer and pump sets are in progress

Koothuparamba Proj AE 2
Date: 23/02/2023

Work in progress | 47% Completed

Erection of transformer and pump sets are in progress

Attached images

img

Koothuparamba Proj AE 2
Date: 17/02/2023

Work in progress | 42% Completed

Erection of transformer and pump sets are in progress

Koothuparamba Proj AE 2
Date: 14/02/2023

Work in progress | 41% Completed

Erection of transformer and pump sets are in progress

Koothuparamba Proj AE 2
Date: 10/02/2023

Work in progress | 40% Completed

Trasformer supplied at site ,work on progress.

Koothuparamba Proj AE 2
Date: 08/02/2023

Work in progress | 35% Completed

Pumpset supplied at site ,work on progress.

Koothuparamba Proj AE 2
Date: 07/02/2023

Work in progress | 23% Completed

Earthing at Substation yard completed as per the direction of electrical inspectorate, Pumpset supplied at site ,work on progress.

Koothuparamba Proj AE 2
Date: 04/02/2023

Work in progress | 21% Completed

Earthing at Substation yard completed as per the direction of electrical inspectorate, Pumpset supplied at site ,work on progress.

Koothuparamba Proj AE 2
Date: 03/02/2023

Work in progress | 20% Completed

Earthing at Substation yard completed as per the direction of electrical inspectorate, Pumpset supplied at site ,work on progress.

Koothuparamba Proj AE 2
Date: 23/01/2023

Work in progress | 19% Completed

Earthing at Substation yard completed as per the direction of electrical inspectorate, Pumpset not supplied .

Koothuparamba Proj AE 2
Date: 18/01/2023

Work in progress | 19% Completed

Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset not supplied .

Koothuparamba Proj AE 2
Date: 11/01/2023

Work in progress | 19% Completed

Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset not supplied .

Koothuparamba Proj AE 2
Date: 28/12/2022

Work in progress | 18% Completed

Earthing completed

Koothuparamba Proj AE 2
Date: 17/12/2022

Work in progress | 17% Completed

Internal wiring of pump houses and electrical room completed

Koothuparamba Proj AE 2
Date: 14/11/2022

Work in progress | 16% Completed

Manufacturing pump set and transformers completed erection work will start by next week. Electrical drawings submitted to electrical inspectorate for approval

Koothuparamba Proj AE 2
Date: 02/11/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 27/10/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 24/10/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 21/10/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 17/10/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 14/10/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 11/10/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 07/10/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 03/10/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 12/09/2022

Work in progress | 16% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 03/09/2022

Work in progress | 15% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 27/08/2022

Work in progress | 15% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 25/08/2022

Work in progress | 6% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 22/08/2022

Work in progress | 6% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 19/08/2022

Work in progress | 6% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 16/08/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 05/08/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 02/08/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 01/08/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 26/07/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed

Koothuparamba Proj AE 2
Date: 23/07/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress

Koothuparamba Proj AE 2
Date: 21/07/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress

Koothuparamba Proj AE 2
Date: 14/07/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress

Koothuparamba Proj AE 2
Date: 09/07/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress

Koothuparamba Proj AE 2
Date: 01/07/2022

Work in progress | 5% Completed

Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress

Koothuparamba Proj AE 2
Date: 09/06/2022

Work has started | 0% Completed

Agreement executed

Koothuparamba Proj AE 2
Date: 03/06/2022

Work has started | 0% Completed

Agreement executed

Koothuparamba Proj AE 2
Date: 29/05/2022

Work has started | 0% Completed

Agreement executed

Koothuparamba Proj AE 2
Date: 23/05/2022

Work has started | 0% Completed

Agreement executed

Koothuparamba Proj AE 2
Date: 18/05/2022

Work has started | 0% Completed

. Agreement executed.

Koothuparamba Proj AE 2
Date: 10/05/2022

Work has started | 0% Completed

Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 05/05/2022

Work has started | 0% Completed

Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 03/05/2022

Work has started | 0% Completed

Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 28/04/2022

Work has started | 0% Completed

Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 25/04/2022

Work has started | 0% Completed

-Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 22/04/2022

Work has started | 0% Completed

Agreement executed

Koothuparamba Proj AE 2
Date: 17/04/2022

Work has started | 0% Completed

Agreement executed.

Koothuparamba Proj AE 2
Date: 12/04/2022

Work has started | 0% Completed

Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 07/04/2022

Work has started | 0% Completed

Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 04/04/2022

Work has started | 0% Completed

Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 02/04/2022

Work has started | 0% Completed

Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 30/03/2022

Work has started | 0% Completed

Work order issued. Agreement executed.

Koothuparamba Proj AE 2
Date: 24/03/2022

Work in progress | 1% Completed

Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted.

Koothuparamba Proj AE 2
Date: 21/03/2022

Work in progress | 1% Completed

Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted.

Koothuparamba Proj AE 2
Date: 17/03/2022

Work in progress | 1% Completed

Site visited by the contractor.Site handed over to the firm

Koothuparamba Proj AE 2
Date: 14/03/2022

Work in progress | 1% Completed

Site visited by the contractor.Site handed over to the firm

Koothuparamba Proj AE 2
Date: 10/03/2022

Work in progress | 1% Completed

Site visited by the contractor.Site handed over to the firm

Koothuparamba Proj AE 2
Date: 07/03/2022

Work has started | 0% Completed

Work order issued. Agreement executed

Koothuparamba Proj AE 2
Date: 06/03/2022

Work has started | 0% Completed

Work order issued. Agreement executed

Koothuparamba Proj AE 2
Date: 02/03/2022

Work has started | 0% Completed

Work order issued. Agreement executed

Koothuparamba Proj AE 2
Date: 27/02/2022

Work has started | 0% Completed

work order issued.Agreement executed

Koothuparamba Proj AE 2
Date: 24/02/2022

Work has started | 0% Completed

Work order issued.

Koothuparamba Proj AE 2
Date: 21/02/2022

Work has started | 0% Completed

Work order issued.

Koothuparamba Proj AE 2
Date: 17/02/2022

Work has started | 0% Completed

Work order issued.

Koothuparamba Proj AE 2
Date: 14/02/2022

Work has started | 0% Completed

Work order issued.

Koothuparamba Proj AE 2
Date: 11/02/2022

Work has started | 0% Completed

Work order isued

Koothuparamba Proj AE 2
Date: 07/02/2022

Work has started | 0% Completed

Tendered. 2 offers received.

Koothuparamba Proj AE 2
Date: 06/02/2022

Work has started | 0% Completed

Bid opened.2 offers received.

Koothuparamba Proj AE 2
Date: 03/02/2022

Work has started | 0% Completed

Tendered.Due date is over.Date of bid opening is 3/02/22

Koothuparamba Proj AE 2
Date: 02/02/2022

Work has started | 0% Completed

Tendered.Due date is over.Date of bid opening is 3/02/22