| Koothuparamba Proj AE 2 |
| Date: 07/06/2024 |
Work has been completed | 100% Completed
Commissioned on 23/5/2024
| Koothuparamba Proj AE 2 |
| Date: 03/06/2024 |
Work has been completed | 100% Completed
Commissioned on 23/5/2024
| Koothuparamba Proj AE 2 |
| Date: 29/05/2024 |
Work has been completed | 100% Completed
Commissioned on 23/5/2024
| Koothuparamba Proj AE 2 |
| Date: 25/05/2024 |
Work has been completed | 100% Completed
Commissioned on 23/5/2024
| Koothuparamba Proj AE 2 |
| Date: 21/05/2024 |
Work in progress | 99% Completed
Pumpset and transformer commisioning on prgress
| Koothuparamba Proj AE 2 |
| Date: 02/05/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection
| Koothuparamba Proj AE 2 |
| Date: 18/04/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection
| Koothuparamba Proj AE 2 |
| Date: 15/04/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection
| Koothuparamba Proj AE 2 |
| Date: 11/04/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection
| Koothuparamba Proj AE 2 |
| Date: 05/04/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection
| Koothuparamba Proj AE 2 |
| Date: 02/04/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection
| Koothuparamba Proj AE 2 |
| Date: 28/03/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection
| Koothuparamba Proj AE 2 |
| Date: 21/03/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection.
| Koothuparamba Proj AE 2 |
| Date: 19/03/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection.
| Koothuparamba Proj AE 2 |
| Date: 14/03/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection.
| Koothuparamba Proj AE 2 |
| Date: 11/03/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection.
| Koothuparamba Proj AE 2 |
| Date: 07/03/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection.
| Koothuparamba Proj AE 2 |
| Date: 04/03/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection.
| Koothuparamba Proj AE 2 |
| Date: 29/02/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection.
| Koothuparamba Proj AE 2 |
| Date: 25/02/2024 |
Work in progress | 99% Completed
Demand note recieved from KSEB for power connection.
| Koothuparamba Proj AE 2 |
| Date: 14/02/2024 |
Work in progress | 99% Completed
Waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 05/02/2024 |
Work in progress | 99% Completed
Waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 30/01/2024 |
Work in progress | 99% Completed
Waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 23/01/2024 |
Work in progress | 99% Completed
Waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 17/01/2024 |
Work in progress | 99% Completed
Waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 01/01/2024 |
Work in progress | 99% Completed
Waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 12/12/2023 |
Work in progress | 99% Completed
All the erection work completed and commissioning pending due to delay in getting safety certification from electrical inspectorate
| Koothuparamba Proj AE 2 |
| Date: 02/11/2023 |
Work in progress | 99% Completed
Waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 19/10/2023 |
Work in progress | 99% Completed
Waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 06/10/2023 |
Work in progress | 99% Completed
Waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 13/09/2023 |
Work in progress | 99% Completed
waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 10/08/2023 |
Work in progress | 99% Completed
waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 03/08/2023 |
Work in progress | 99% Completed
waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 26/07/2023 |
Work in progress | 99% Completed
waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 19/07/2023 |
Work in progress | 99% Completed
waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 11/07/2023 |
Work in progress | 99% Completed
waiting for KSEB connection
| Koothuparamba Proj AE 2 |
| Date: 05/07/2023 |
Work in progress | 99% Completed
waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 30/06/2023 |
Work in progress | 99% Completed
waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 23/06/2023 |
Work in progress | 99% Completed
waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 19/06/2023 |
Work in progress | 99% Completed
waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 12/06/2023 |
Work in progress | 97% Completed
waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 06/06/2023 |
Work in progress | 97% Completed
waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 01/06/2023 |
Work in progress | 97% Completed
Finishing work on progress, waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 25/05/2023 |
Work in progress | 97% Completed
Finishing work on progress,waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 22/05/2023 |
Work in progress | 97% Completed
Finishing work on progress,waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 17/05/2023 |
Work in progress | 97% Completed
Finishing work on progress,waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 10/05/2023 |
Work in progress | 96% Completed
Finishing work on progress,waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 08/05/2023 |
Work in progress | 95% Completed
Finishing work on progress,waiting for safety certification from KSEB
| Koothuparamba Proj AE 2 |
| Date: 04/05/2023 |
Work in progress | 87% Completed
Pump interconnection work ongoing.Fencing work on progress,lighting work on progress
| Koothuparamba Proj AE 2 |
| Date: 28/04/2023 |
Work in progress | 86% Completed
Pump interconnection work ongoing.Fencing work on progress
| Koothuparamba Proj AE 2 |
| Date: 24/04/2023 |
Work in progress | 85% Completed
erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.Fencing work on progress
| Koothuparamba Proj AE 2 |
| Date: 18/04/2023 |
Work in progress | 81% Completed
erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.
| Koothuparamba Proj AE 2 |
| Date: 05/04/2023 |
Work in progress | 80% Completed
erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.
| Koothuparamba Proj AE 2 |
| Date: 30/03/2023 |
Work in progress | 78% Completed
erection of transformer ongaoing , termination work ongoing
| Koothuparamba Proj AE 2 |
| Date: 16/03/2023 |
Work in progress | 75% Completed
Erection of transformer are in progress
| Koothuparamba Proj AE 2 |
| Date: 09/03/2023 |
Work in progress | 70% Completed
Erection of transformer are in progress
| Koothuparamba Proj AE 2 |
| Date: 04/03/2023 |
Work in progress | 68% Completed
Pumpset erection work completed
| Koothuparamba Proj AE 2 |
| Date: 02/03/2023 |
| Koothuparamba Proj AE 2 |
| Date: 01/03/2023 |
Work in progress | 55% Completed
Erection of transformer and pump sets are in progress
| Koothuparamba Proj AE 2 |
| Date: 23/02/2023 |
| Koothuparamba Proj AE 2 |
| Date: 17/02/2023 |
Work in progress | 42% Completed
Erection of transformer and pump sets are in progress
| Koothuparamba Proj AE 2 |
| Date: 14/02/2023 |
Work in progress | 41% Completed
Erection of transformer and pump sets are in progress
| Koothuparamba Proj AE 2 |
| Date: 10/02/2023 |
Work in progress | 40% Completed
Trasformer supplied at site ,work on progress.
| Koothuparamba Proj AE 2 |
| Date: 08/02/2023 |
Work in progress | 35% Completed
Pumpset supplied at site ,work on progress.
| Koothuparamba Proj AE 2 |
| Date: 07/02/2023 |
Work in progress | 23% Completed
Earthing at Substation yard completed as per the direction of electrical inspectorate, Pumpset supplied at site ,work on progress.
| Koothuparamba Proj AE 2 |
| Date: 04/02/2023 |
Work in progress | 21% Completed
Earthing at Substation yard completed as per the direction of electrical inspectorate, Pumpset supplied at site ,work on progress.
| Koothuparamba Proj AE 2 |
| Date: 03/02/2023 |
Work in progress | 20% Completed
Earthing at Substation yard completed as per the direction of electrical inspectorate, Pumpset supplied at site ,work on progress.
| Koothuparamba Proj AE 2 |
| Date: 23/01/2023 |
Work in progress | 19% Completed
Earthing at Substation yard completed as per the direction of electrical inspectorate, Pumpset not supplied .
| Koothuparamba Proj AE 2 |
| Date: 18/01/2023 |
Work in progress | 19% Completed
Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset not supplied .
| Koothuparamba Proj AE 2 |
| Date: 11/01/2023 |
Work in progress | 19% Completed
Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset not supplied .
| Koothuparamba Proj AE 2 |
| Date: 28/12/2022 |
Work in progress | 18% Completed
Earthing completed
| Koothuparamba Proj AE 2 |
| Date: 17/12/2022 |
Work in progress | 17% Completed
Internal wiring of pump houses and electrical room completed
| Koothuparamba Proj AE 2 |
| Date: 14/11/2022 |
Work in progress | 16% Completed
Manufacturing pump set and transformers completed erection work will start by next week. Electrical drawings submitted to electrical inspectorate for approval
| Koothuparamba Proj AE 2 |
| Date: 02/11/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 27/10/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 24/10/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 21/10/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 17/10/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 14/10/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 11/10/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 07/10/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 03/10/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 12/09/2022 |
Work in progress | 16% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 03/09/2022 |
Work in progress | 15% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 27/08/2022 |
Work in progress | 15% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 25/08/2022 |
Work in progress | 6% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 22/08/2022 |
Work in progress | 6% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 19/08/2022 |
Work in progress | 6% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 16/08/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 05/08/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 02/08/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 01/08/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 26/07/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed
| Koothuparamba Proj AE 2 |
| Date: 23/07/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress
| Koothuparamba Proj AE 2 |
| Date: 21/07/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress
| Koothuparamba Proj AE 2 |
| Date: 14/07/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress
| Koothuparamba Proj AE 2 |
| Date: 09/07/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress
| Koothuparamba Proj AE 2 |
| Date: 01/07/2022 |
Work in progress | 5% Completed
Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers in progress
| Koothuparamba Proj AE 2 |
| Date: 09/06/2022 |
Work has started | 0% Completed
Agreement executed
| Koothuparamba Proj AE 2 |
| Date: 03/06/2022 |
Work has started | 0% Completed
Agreement executed
| Koothuparamba Proj AE 2 |
| Date: 29/05/2022 |
Work has started | 0% Completed
Agreement executed
| Koothuparamba Proj AE 2 |
| Date: 23/05/2022 |
Work has started | 0% Completed
Agreement executed
| Koothuparamba Proj AE 2 |
| Date: 18/05/2022 |
Work has started | 0% Completed
. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 10/05/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 05/05/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 03/05/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 28/04/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 25/04/2022 |
Work has started | 0% Completed
-Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 22/04/2022 |
Work has started | 0% Completed
Agreement executed
| Koothuparamba Proj AE 2 |
| Date: 17/04/2022 |
Work has started | 0% Completed
Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 12/04/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 07/04/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 04/04/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 02/04/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 30/03/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed.
| Koothuparamba Proj AE 2 |
| Date: 24/03/2022 |
Work in progress | 1% Completed
Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted.
| Koothuparamba Proj AE 2 |
| Date: 21/03/2022 |
Work in progress | 1% Completed
Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted.
| Koothuparamba Proj AE 2 |
| Date: 17/03/2022 |
Work in progress | 1% Completed
Site visited by the contractor.Site handed over to the firm
| Koothuparamba Proj AE 2 |
| Date: 14/03/2022 |
Work in progress | 1% Completed
Site visited by the contractor.Site handed over to the firm
| Koothuparamba Proj AE 2 |
| Date: 10/03/2022 |
Work in progress | 1% Completed
Site visited by the contractor.Site handed over to the firm
| Koothuparamba Proj AE 2 |
| Date: 07/03/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed
| Koothuparamba Proj AE 2 |
| Date: 06/03/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed
| Koothuparamba Proj AE 2 |
| Date: 02/03/2022 |
Work has started | 0% Completed
Work order issued. Agreement executed
| Koothuparamba Proj AE 2 |
| Date: 27/02/2022 |
Work has started | 0% Completed
work order issued.Agreement executed
| Koothuparamba Proj AE 2 |
| Date: 24/02/2022 |
Work has started | 0% Completed
Work order issued.
| Koothuparamba Proj AE 2 |
| Date: 21/02/2022 |
Work has started | 0% Completed
Work order issued.
| Koothuparamba Proj AE 2 |
| Date: 17/02/2022 |
Work has started | 0% Completed
Work order issued.
| Koothuparamba Proj AE 2 |
| Date: 14/02/2022 |
Work has started | 0% Completed
Work order issued.
| Koothuparamba Proj AE 2 |
| Date: 11/02/2022 |
Work has started | 0% Completed
Work order isued
| Koothuparamba Proj AE 2 |
| Date: 07/02/2022 |
Work has started | 0% Completed
Tendered. 2 offers received.
| Koothuparamba Proj AE 2 |
| Date: 06/02/2022 |
Work has started | 0% Completed
Bid opened.2 offers received.
| Koothuparamba Proj AE 2 |
| Date: 03/02/2022 |
Work has started | 0% Completed
Tendered.Due date is over.Date of bid opening is 3/02/22
| Koothuparamba Proj AE 2 |
| Date: 02/02/2022 |
Work has started | 0% Completed
Tendered.Due date is over.Date of bid opening is 3/02/22