NABARD - Kottiyoor,Kelakam and Kanichar Panchayath- Supply and erection of 315KVA Transformer and Pumpsets at Intake well - Package V

Project NABARD - Kottiyoor,Kelakam and Kanichar Panchayath- Supply and erection of 315KVA Transformer and Pumpsets at Intake well - Package V
Project Code KNRNABARD12173151P5
Type Package
Main Project NABARD -RIDF-XXIII- WSS to Kottiyoor, Kelakam and Kanichar Panchayaths in Iritty Taluk of Kannur District - Phase I
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme 4215-01-102-98 (01)
Description Supply and erection of 315 KVA transformer and 3 Nos pupmsets at Intake well, Kalikayam
Status On-going
District Kannur
Executing Office Koothuparamba Project Sn No2
Agreement Number
Agreement Date
TS Amount (Rs) 15900000
TS Number TS/2021-2022/2021/35420
Technical specification Supply and erection of 315 KVA transformer and 3 nos pupmsets at Intake well, Kalikayam
Contractor M/S Premier Power Line,4/350-A.Govindanaickenpalayam,K.Valasu Post, (Mob: 9842773035)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/02/2022
Scheduled date of Completion as per agreement 08 Jun 2022
Expected date of Completion 05/03/2024

Processing Dates

TS Date 27 Dec 2021
Estimate Approval 27 Dec 2021
NIT Approval 03 Mar 2022
Tender Closing 01 Feb 2022
Technichal Pre-Qualification 08 Aug 2022
Price bid opening 03 Feb 2022

Approval Dates

Workorder Date 08 Feb 2022
NA 25 Feb 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koothuparamba Proj AE 2
Date: 07/06/2024

Work has been completed | 100% Completed

Commissioned on 23/5/2024.

Koothuparamba Proj AE 2
Date: 03/06/2024

Work has been completed | 100% Completed

Commissioned on 23/5/2024.