Kanjiramkulam AE JJM |
Date: 28/06/2022 |
Work has been completed | 100% Completed
CC 3rd and final bill submitted
Kanjiramkulam AE JJM |
Date: 15/06/2022 |
Work has been completed | 100% Completed
final bill submitted for 368 nos FHTC
Kanjiramkulam AE JJM |
Date: 13/06/2022 |
Work has been completed | 100% Completed
work completed
Kanjiramkulam AE JJM |
Date: 09/06/2022 |
Work has been completed | 100% Completed
work completed
Kanjiramkulam AE JJM |
Date: 06/06/2022 |
Work has been completed | 100% Completed
work completed
Kanjiramkulam AE JJM |
Date: 02/06/2022 |
Work has been completed | 100% Completed
work completed final bill under preparation
Kanjiramkulam AE JJM |
Date: 30/05/2022 |
Work has been completed | 100% Completed
work completed
Kanjiramkulam AE JJM |
Date: 26/05/2022 |
Work in progress | 97% Completed
e service is going on and road restoration work in progress
Kanjiramkulam AE JJM |
Date: 23/05/2022 |
Work in progress | 96% Completed
364 nos fhtc given, e service is going on
Kanjiramkulam AE JJM |
Date: 20/05/2022 |
Work in progress | 96% Completed
out of 325 nos fhtc 340 nos given
Kanjiramkulam AE JJM |
Date: 16/05/2022 |
Work in progress | 95% Completed
out of 325 nos FHTC 330 nos given
Kanjiramkulam AE JJM |
Date: 11/05/2022 |
Work in progress | 90% Completed
300 nos fhtc given
Kanjiramkulam AE JJM |
Date: 07/05/2022 |
Work in progress | 80% Completed
230 nos fhtc given
Kanjiramkulam AE JJM |
Date: 04/05/2022 |
Work in progress | 75% Completed
CC 2nd and part bill submitted
Kanjiramkulam AE JJM |
Date: 28/04/2022 |
Work in progress | 70% Completed
210 nos FHTC given, waiting for 20 mm HDPE additional length
Kanjiramkulam AE JJM |
Date: 25/04/2022 |
Work in progress | 65% Completed
190 nos FHTC given
Kanjiramkulam AE JJM |
Date: 22/04/2022 |
Work in progress | 60% Completed
164 nos fhtc given
Neyyattinkara WS Dn EE |
Date: 21/04/2022 |
Work in progress | 55% Completed
Work in progress
Neyyattinkara WS Dn EE |
Date: 20/04/2022 |
Work in progress | 55% Completed
Work in progress
Neyyattinkara WS Dn EE |
Date: 19/04/2022 |
Work in progress | 55% Completed
Work in progress
Kanjiramkulam AE JJM |
Date: 18/04/2022 |
Work in progress | 55% Completed
replacement of AC pipe work completed and 140 nos fhtc given
Kanjiramkulam AE JJM |
Date: 16/04/2022 |
Work in progress | 50% Completed
130 nos fhtc given
Kanjiramkulam AE JJM |
Date: 11/04/2022 |
Work in progress | 45% Completed
110 nos FHTC given
Kanjiramkulam AE JJM |
Date: 07/04/2022 |
Work in progress | 40% Completed
90 nos FHTC given
Kanjiramkulam AE JJM |
Date: 04/04/2022 |
Work in progress | 36% Completed
72 nos FHTC given
Kanjiramkulam AE JJM |
Date: 30/03/2022 |
Work in progress | 35% Completed
60 nos fhtc given CC 1st and part bill for 50 nos fhtc submitted
Kanjiramkulam AE JJM |
Date: 25/03/2022 |
Work in progress | 32% Completed
50 NOS FHTC GIVEN
Kanjiramkulam AE JJM |
Date: 24/03/2022 |
Work in progress | 30% Completed
replacement of AC pipe with alteration of connection completed
Kanjiramkulam AE JJM |
Date: 21/03/2022 |
Work in progress | 28% Completed
45 nos HTC given
Neyyattinkara WS Dn EE |
Date: 18/03/2022 |
Work in progress | 25% Completed
replacement of AC pipe at Pambukala road completed
Kanjiramkulam AE JJM |
Date: 15/03/2022 |
Work in progress | 24% Completed
37nos FHTC given, replacement of AC PIPE 90% COMPLETED
Kanjiramkulam AE JJM |
Date: 09/03/2022 |
Work in progress | 18% Completed
Replacement of AC pipe with alteration of existing connection work 90 % completed
Kanjiramkulam AE JJM |
Date: 07/03/2022 |
Work in progress | 15% Completed
30 nos FHTC completed
Kanjiramkulam AE JJM |
Date: 05/03/2022 |
Work in progress | 10% Completed
24 nos FHTC given replacement of AC with pvc pipe at pambukaala-poovar road in prrogres
Kanjiramkulam AE JJM |
Date: 02/03/2022 |
Work in progress | 6% Completed
18 nos FHTC completed
Kanjiramkulam AE JJM |
Date: 28/02/2022 |
Work in progress | 5% Completed
13 nos FHTC completed
Kanjiramkulam AE JJM |
Date: 26/02/2022 |
Work in progress | 2% Completed
9 nos FHTC given and replacement of AC at Poovar Pambukala road in progress
Kanjiramkulam AE JJM |
Date: 24/02/2022 |
Work in progress | 1% Completed
5 nos FHTC Given
Kanjiramkulam AE JJM |
Date: 21/02/2022 |
Work in progress | 1% Completed
Replacement of AC pipe work started.
Neyyattinkara WS Dn EE |
Date: 18/02/2022 |
Work in progress | 1% Completed
Work in progress
Kanjiramkulam AE JJM |
Date: 14/02/2022 |
Work in progress | 1% Completed
work started 2 Nos FHTC given
Kanjiramkulam AE JJM |
Date: 09/02/2022 |
Work in progress | 1% Completed
Replacement of AC -160mm pvc pipe supplied
Kanjiramkulam AE JJM |
Date: 05/02/2022 |
Work has started | 0% Completed
pipe not yet received, supply order placed by the contractor
Kanjiramkulam AE JJM |
Date: 03/02/2022 |
Work has started | 0% Completed
Demand notice for Tar cutting received from PWD, recorded and submitted to Division office
Kanjiramkulam AE JJM |
Date: 31/01/2022 |
Work has started | 0% Completed
pipes not yet received
Kanjiramkulam AE JJM |
Date: 27/01/2022 |
Work has started | 0% Completed
supply of pipe order placed by the contractor
Kanjiramkulam AE JJM |
Date: 21/01/2022 |
Work has started | 0% Completed
supply of pipe-order given by conractor
Kanjiramkulam AE JJM |
Date: 19/01/2022 |
Work has started | 0% Completed
selection of beneficiaries houses is going on