Project | JJM 2020-21- (Phase 2) reach-II -Providing FHTCS to house holds through retrofitting and replacement of old AC pipes 750 m Poovar- Paampukala road and giving FHTCs 325 nos to HH.to |
---|---|
Project Code | TVMJJM10208504P1 |
Type | Package |
Main Project | JJM 2020-21- Providing FHTCS to house holds through retrofitting and replacement of old AC pipes 750m from Pambukaala - Poovar road (Phase 2) reach-II, giving 325 nos FHTC s in Poovar Panchayat. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM 2020-21- (Phase 2) reach-II -Providing FHTCS to house holds through retrofitting and replacement of old AC pipes 750 m Paampukaala - Poovar road with alteration of existing connections and giving 325 nos. FHTC s to HH and providing additional length 20 mm PE pipe 3000m .25 mm PE pipe1250m |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Kanjiramkulam WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9980000 |
TS Number | TS/2021-2022/2021/3458 DATED 29/11/2021. |
Technical specification | -Providing FHTCS to house holds through retrofitting and replacement of old AC pipes 750 m Paampukaala - Poovar road with alteration of existing connections and giving 325 nos. FHTC s to HH and providing additional length 20 mm PE pipe 3000m .25 mm PE pipe1250m etc. |
Contractor | DILEEP.P.B (Mob: 9895262424) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 27/12/2021 |
---|---|
Scheduled date of Completion as per agreement | 14 Mar 2022 |
Expected date of Completion | 14/03/2022 |
TS Date | 29 Nov 2021 |
---|---|
Estimate Approval | 29 Nov 2021 |
NIT Approval | 13 Dec 2021 |
Tender Closing | 10 Dec 2021 |
Technichal Pre-Qualification | 10 Dec 2021 |
Price bid opening | 13 Dec 2021 |
NA | 06 Jan 2022 |
---|---|
Workorder Date | 27 Dec 2021 |
Kanjiramkulam AE JJM |
Date: 28/06/2022 |
Work has been completed | 100% Completed
CC 3rd and final bill submitted.
Kanjiramkulam AE JJM |
Date: 15/06/2022 |
Work has been completed | 100% Completed
final bill submitted for 368 nos FHTC.