Thrissur PH Dn EE
Date: 03/07/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Guruvayur PH Sn AE
Date: 29/06/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Thrissur PH Dn EE
Date: 28/06/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Guruvayur PH Sn AE
Date: 24/06/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Guruvayur PH Sn AE
Date: 19/06/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Guruvayur PH Sn AE
Date: 15/06/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Guruvayur PH Sn AE
Date: 14/06/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Guruvayur PH Sn AE
Date: 10/06/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Guruvayur PH Sn AE
Date: 05/06/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Thrissur PH Dn EE
Date: 03/06/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Thrissur PH Dn EE
Date: 30/05/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Thrissur PH Dn EE
Date: 29/05/2024

Work in progress | 90% Completed

Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation

Guruvayur PH Sn AE
Date: 27/05/2024

Work in progress | 80% Completed

Part Bill Submitted

Guruvayur PH Sn AE
Date: 22/05/2024

Work in progress | 80% Completed

Part Bill Submitted

Guruvayur PH Sn AE
Date: 17/05/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 13/05/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 07/05/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 03/05/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 29/04/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 24/04/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 20/04/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 19/04/2024

Work in progress | 80% Completed

Part Bill Submitted.

Thrissur PH Dn EE
Date: 18/04/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 16/04/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 12/04/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 08/04/2024

Work in progress | 80% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 03/04/2024

Work in progress | 70% Completed

Part Bill Submitted.

Thrissur PH Dn EE
Date: 30/03/2024

Work in progress | 70% Completed

Part Bill Submitted.

Guruvayur PH Sn AE
Date: 26/03/2024

Work in progress | 70% Completed

Part Bill Submitted

Guruvayur PH Sn AE
Date: 25/03/2024

Work in progress | 70% Completed

Part Bill Submitted

Guruvayur PH Sn AE
Date: 20/03/2024

Work in progress | 70% Completed

Part Bill Submitted

Guruvayur PH Sn AE
Date: 16/03/2024

Work in progress | 70% Completed

Part Bill Submitted

Guruvayur PH Sn AE
Date: 13/03/2024

Work in progress | 70% Completed

Part Bill Submitted

Guruvayur PH Sn AE
Date: 11/03/2024

Work in progress | 70% Completed

Work Ongoing, Tarring work completed

Guruvayur PH Sn AE
Date: 05/03/2024

Work in progress | 50% Completed

Work Ongoing, Tarring work completed

Thrissur PH Dn EE
Date: 01/03/2024

Work in progress | 46% Completed

Work Ongoing, Tarring work ongoing

Guruvayur PH Sn AE
Date: 28/02/2024

Work in progress | 46% Completed

Work Ongoing,Tariyng work ongoing

Guruvayur PH Sn AE
Date: 27/02/2024

Work in progress | 41% Completed

Work Ongoing, GSB filling work started--1800.

Thrissur PH Dn EE
Date: 24/02/2024

Work in progress | 41% Completed

Work Ongoing, GSB filling work started--1800.

Guruvayur PH Sn AE
Date: 21/02/2024

Work in progress | 41% Completed

Work Ongoing, GSB filling work started--1800

Thrissur PH Dn EE
Date: 19/02/2024

Work in progress | 38% Completed

Work Ongoing, GSB filling work started--1800

Thrissur PH Dn EE
Date: 17/02/2024

Work in progress | 38% Completed

Work Ongoing, GSB filling work started--1800

Guruvayur PH Sn AE
Date: 12/02/2024

Work in progress | 38% Completed

Work Ongoing, GSB filling work started--1800

Guruvayur PH Sn AE
Date: 09/02/2024

Work in progress | 38% Completed

Work Ongoing, GSB filling work started--1800

Thrissur PH Dn EE
Date: 06/02/2024

Work in progress | 32% Completed

Work Ongoing, GSB filling work started--1800

Guruvayur PH Sn AE
Date: 02/02/2024

Work in progress | 28% Completed

Work Ongoing, GSB filling work started

Guruvayur PH Sn AE
Date: 30/01/2024

Work in progress | 2% Completed

Ongoing, GSB filling work started

Guruvayur PH Sn AE
Date: 29/01/2024

Work in progress | 2% Completed

Ongoing, GSB filling work started

Guruvayur PH Sn AE
Date: 27/01/2024

Work in progress | 2% Completed

Ongoing, GSB filling work started

Guruvayur PH Sn AE
Date: 24/01/2024

Work in progress | 2% Completed

Ongoing, GSB filling work started

Guruvayur PH Sn AE
Date: 20/01/2024

Work in progress | 1% Completed

Ongoing

Guruvayur PH Sn AE
Date: 18/01/2024

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 17/01/2024

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 16/01/2024

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 15/01/2024

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 12/01/2024

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 08/01/2024

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 06/01/2024

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 04/01/2024

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 03/01/2024

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Thrissur PH Dn EE
Date: 30/12/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 26/12/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Thrissur PH Dn EE
Date: 20/12/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 16/12/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 14/12/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 11/12/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 06/12/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 02/12/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 28/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 25/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 24/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 22/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 17/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 16/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 13/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 07/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 03/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 01/11/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 28/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 27/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 26/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Thrissur PH Dn EE
Date: 25/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 20/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 16/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 10/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Thrissur PH Dn EE
Date: 07/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 04/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 03/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Thrissur PH Dn EE
Date: 02/10/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 29/09/2023

Work in progress | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Thrissur PH Dn EE
Date: 27/09/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 23/09/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 21/09/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 20/09/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Guruvayur PH Sn AE
Date: 18/09/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Thrissur PH Dn EE
Date: 16/09/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023

Thrissur PH Dn EE
Date: 12/09/2023

Work has started | 0% Completed

Work order issued on 17.08.2023. Agreement executed on 08.09.2023