Project | Jal Jeevan Mission (JJM)- Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath -4th SLSSC--Part III - Extension of distribution line - Road restoration work(Phase 1)-Pipeline Work |
---|---|
Project Code | TCRJJM022214760P3 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath-- 4th SLSSC |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)- Jal Jeevan Mission Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath -4th SLSSC--Part III - Extension of distribution line - Road restoration work(Phase 1)-Pipeline Work |
Status | On-going |
District | Thrissur |
Executing Office | Guruvayur PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 7437400 |
TS Number | WRD/KWA-CE(CR)/EST_TS/17731/2023_26_1_1 Dated: 02-08-2023 |
Technical specification | Providing line extension and Functional House Hold Tap connection FHTC'S at Orumanayur Panchayath -4th SLSSC--Part III - Extension of distribution line - Road restoration work(Phase 1)-Pipeline Work |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/08/2023 |
---|---|
Scheduled date of Completion as per agreement | 16 Nov 2023 |
Expected date of Completion | 31/07/2024 |
TS Date | 02 Aug 2023 |
---|---|
Estimate Approval | 02 Aug 2023 |
NIT Approval | 02 Aug 2023 |
Tender Closing | 09 Aug 2023 |
Technichal Pre-Qualification | 09 Aug 2023 |
Price bid opening | 10 Aug 2023 |
Workorder Date | 17 Aug 2023 |
---|---|
NA | 08 Sep 2023 |
Guruvayur PH Sn AE |
Date: 29/06/2024 |
Work in progress | 90% Completed
Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation .
Thrissur PH Dn EE |
Date: 28/06/2024 |
Work in progress | 90% Completed
Road Restoration work ongoing, 90% restoration completed. 2nd and part bill submitted to Division. Revised estimate under preparation.