| Madathara PH Sn - AE |
| Date: 14/07/2025 |
Work has been completed | 100% Completed
Work completed
| Kottarakkara PH Dn EE |
| Date: 10/03/2025 |
Work in progress | 70% Completed
Pipe line work-80% Tank work-80% Pump House-50%
| Kottarakkara PH Dn EE |
| Date: 21/12/2024 |
Work in progress | 1% Completed
Work Started
| Kottarakkara PH Dn EE |
| Date: 21/11/2024 |
Work in progress | 0% Completed
Agreement executed
| Kottarakkara PH Dn EE |
| Date: 29/10/2024 |
Work has started | 0% Completed
Tender opening on 29/10/24
| Kottarakkara PH Dn EE |
| Date: 25/10/2024 |
Work has started | 0% Completed
On tender stage