Mankada AE
Date: 12/08/2023

Work has been completed | 100% Completed

All pipe line laying work completed. The work includes 870 nos of FHTC, out of this 623 FHTC has been completed. The remaining 247 nos of FHTCs can be provided only after completion of the ongoing pipe laying work of Project Division, Malappuram. JJM Phase 2 package 5 is ongoing work and if there is any further demand for FHTCs from consumer side, it can be completed under package 5. Hence considering the the above facts package 4 under JJM Phase II may be considered as completed.

Mankada AE
Date: 09/08/2023

Work in progress | 56% Completed

All pipe line laying work completed. Total 591 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement

Mankada AE
Date: 05/08/2023

Work in progress | 56% Completed

All pipe line laying work completed. Total 550 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement

Mankada AE
Date: 01/08/2023

Work in progress | 56% Completed

All pipe line laying work completed. Total 550 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement

Mankada AE
Date: 29/07/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 535 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement

Mankada AE
Date: 24/07/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 535 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement

Mankada AE
Date: 19/07/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 520 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement

Mankada AE
Date: 14/07/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement

Mankada AE
Date: 10/07/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements.

Mankada AE
Date: 04/07/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements.

Mankada AE
Date: 30/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements.

Mankada AE
Date: 26/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements.

Mankada AE
Date: 21/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements

Mankada AE
Date: 19/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements

Mankada AE
Date: 15/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements

Mankada AE
Date: 12/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements

Mankada AE
Date: 08/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements

Mankada AE
Date: 06/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 03/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 02/06/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 29/05/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 25/05/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 22/05/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 17/05/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 15/05/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 12/05/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Malappuram PH Dn EE
Date: 09/05/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 05/05/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 02/05/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 25/04/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 20/04/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 17/04/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 13/04/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 10/04/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 04/04/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 31/03/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 24/03/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 20/03/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 14/03/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 10/03/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 06/03/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 02/03/2023

Work in progress | 55% Completed

Package 3 and 1 completed, Package 2, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-710 FHTCs completed, Package 4-500 FHTCs completed

Mankada AE
Date: 28/02/2023

Work in progress | 55% Completed

Package 3 and 1 completed, Package 2, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-710 FHTCs completed, Package 4-500 FHTCs completed

Mankada AE
Date: 24/02/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 22/02/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 17/02/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 14/02/2023

Work in progress | 55% Completed

All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme

Mankada AE
Date: 10/02/2023

Work in progress | 26% Completed

Total 500 FHTCs completed ,out of which 494 FHTC geotagged.

Mankada AE
Date: 04/02/2023

Work in progress | 26% Completed

Total 500 FHTCs completed ,out of which 494 FHTC geotagged.

Mankada AE
Date: 31/01/2023

Work in progress | 26% Completed

Total 500 FHTCs completed ,out of which 494 FHTC geotagged.

Mankada AE
Date: 24/01/2023

Work in progress | 25% Completed

Total 500 FHTCs completed ,out of which 494 FHTC geotagged.

Mankada AE
Date: 17/01/2023

Work in progress | 24% Completed

Total 455 FHTCs completed ,out of which 455 FHTC geotagged.

Mankada AE
Date: 11/01/2023

Work in progress | 24% Completed

Total 455 FHTCs completed ,out of which 455 FHTC geotagged.

Mankada AE
Date: 07/01/2023

Work in progress | 24% Completed

Total 455 FHTCs completed ,out of which 455 FHTC geotagged.

Mankada AE
Date: 03/01/2023

Work in progress | 24% Completed

Total 455 FHTCs completed ,out of which 455 FHTC geotagged.

Mankada AE
Date: 28/12/2022

Work in progress | 24% Completed

Total 455 FHTCs completed ,out of which 455 FHTC geotagged.

Mankada AE
Date: 21/12/2022

Work in progress | 20% Completed

Total 256 FHTCs completed ,out of which 241 FHTC geotagged.

Mankada AE
Date: 17/12/2022

Work in progress | 20% Completed

Total 241 FHTCs completed ,out of which 241 FHTC geotagged.

Mankada AE
Date: 12/12/2022

Work in progress | 17% Completed

Total 160 FHTCs completed ,out of which 40 FHTC geotagged.

Mankada AE
Date: 25/11/2022

Work in progress | 17% Completed

Total 150 FHTCs completed ,out of which 36 FHTC geotagged.

Mankada AE
Date: 16/11/2022

Work in progress | 16% Completed

Total 150 FHTCs completed ,out of which 27 FHTC geotagged.

Mankada AE
Date: 11/11/2022

Work in progress | 16% Completed

Total 150 FHTCs completed ,out of which 27 FHTC geotagged.

Mankada AE
Date: 05/11/2022

Work in progress | 15% Completed

8 km Pipe line work going on. Total 150 FHTCs completed ,out of which 25 FHTC geotagged.

Mankada AE
Date: 26/10/2022

Work in progress | 14% Completed

Total 150 FHTCs completed ,out of which 20 FHTC geotagged.

Mankada AE
Date: 17/10/2022

Work in progress | 14% Completed

Total 150 FHTCs completed ,out of which 15 FHTC geotagged.

Mankada AE
Date: 07/10/2022

Work in progress | 13% Completed

Total 150 FHTCs completed ,out of which 12 FHTC geotagged.

Mankada AE
Date: 29/09/2022

Work in progress | 13% Completed

Total 150 FHTCs completed ,out of which 2 FHTC geotagged.

Mankada AE
Date: 24/09/2022

Work in progress | 12% Completed

Completed laying of 2 km distribution lines and 100 FHTC completed but not geotagged

Mankada AE
Date: 19/09/2022

Work in progress | 11% Completed

Completed laying of 2 km distribution lines and 100 FHTC completed but not geotagged

Mankada AE
Date: 14/09/2022

Work in progress | 10% Completed

Completed laying of 2 km distribution lines and 100 FHTC completed but not geotagged

Mankada AE
Date: 05/09/2022

Work in progress | 10% Completed

Completed laying of 2 km distribution lines and 90 FHTC completed but not geotagged

Mankada AE
Date: 01/09/2022

Work in progress | 10% Completed

Completed laying of 2 km distribution lines and 90 FHTC completed but not geotagged

Mankada AE
Date: 26/08/2022

Work in progress | 10% Completed

Completed laying of 2km distribution lines and 90 FHTC completed but not geotagged

Mankada AE
Date: 23/08/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 22/08/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 16/08/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 11/08/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 08/08/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 03/08/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 27/07/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 25/07/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 22/07/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 16/07/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 12/07/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 08/07/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 04/07/2022

Work in progress | 1% Completed

Pipe laying and trenching works ongoing

Mankada AE
Date: 01/07/2022

Work in progress | 0% Completed

Pipe Laying started

Mankada AE
Date: 15/06/2022

Work in progress | 0% Completed

Pipe supplied

Malappuram PH Dn EE
Date: 03/06/2022

Work in progress | 0% Completed

Agreement executed

Malappuram PH Dn EE
Date: 11/05/2022

Work has started | 0% Completed

Agreement executed

Malappuram PH Dn EE
Date: 06/05/2022

Work has started | 0% Completed

package 4- Agreement executed on 08.04.2022

Malappuram PH Dn EE
Date: 26/04/2022

Work has started | 0% Completed

Agreement to be executed

Malappuram PH Dn EE
Date: 19/04/2022

Work has started | 0% Completed

Reversed work order awarded on 26/03/2022

Malappuram PH Dn EE
Date: 23/03/2022

Work has started | 0% Completed

work cancelled retender invited.

Malappuram PH Dn EE
Date: 14/03/2022

Work has started | 0% Completed

work cancelled retender invited.

Malappuram PH Dn EE
Date: 25/02/2022

Work has started | 0% Completed

Agmt not executed. letter given to 2nd lowest

Malappuram PH Dn EE
Date: 18/02/2022

Work has started | 0% Completed

Work order issued on 15.01.2022