Mankada AE |
Date: 12/08/2023 |
Work has been completed | 100% Completed
All pipe line laying work completed. The work includes 870 nos of FHTC, out of this 623 FHTC has been completed. The remaining 247 nos of FHTCs can be provided only after completion of the ongoing pipe laying work of Project Division, Malappuram. JJM Phase 2 package 5 is ongoing work and if there is any further demand for FHTCs from consumer side, it can be completed under package 5. Hence considering the the above facts package 4 under JJM Phase II may be considered as completed.
Mankada AE |
Date: 09/08/2023 |
Work in progress | 56% Completed
All pipe line laying work completed. Total 591 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement
Mankada AE |
Date: 05/08/2023 |
Work in progress | 56% Completed
All pipe line laying work completed. Total 550 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement
Mankada AE |
Date: 01/08/2023 |
Work in progress | 56% Completed
All pipe line laying work completed. Total 550 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement
Mankada AE |
Date: 29/07/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 535 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement
Mankada AE |
Date: 24/07/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 535 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement
Mankada AE |
Date: 19/07/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 520 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement
Mankada AE |
Date: 14/07/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement
Mankada AE |
Date: 10/07/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements.
Mankada AE |
Date: 04/07/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements.
Mankada AE |
Date: 30/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements.
Mankada AE |
Date: 26/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements.
Mankada AE |
Date: 21/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements
Mankada AE |
Date: 19/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements
Mankada AE |
Date: 15/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements
Mankada AE |
Date: 12/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements
Mankada AE |
Date: 08/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements
Mankada AE |
Date: 06/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 03/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 02/06/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 29/05/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 25/05/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 22/05/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 17/05/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 15/05/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 12/05/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Malappuram PH Dn EE |
Date: 09/05/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 05/05/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 02/05/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 25/04/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 20/04/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 17/04/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 13/04/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 10/04/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 04/04/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 31/03/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 24/03/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 20/03/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 14/03/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 10/03/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 06/03/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 02/03/2023 |
Work in progress | 55% Completed
Package 3 and 1 completed, Package 2, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-710 FHTCs completed, Package 4-500 FHTCs completed
Mankada AE |
Date: 28/02/2023 |
Work in progress | 55% Completed
Package 3 and 1 completed, Package 2, Package 4,and package 5 are on going ,package 5-965 FHTCs completed, Package 1- 871 FHTCs completed, Package 3 -877 FHTCs completed, Package 2-710 FHTCs completed, Package 4-500 FHTCs completed
Mankada AE |
Date: 24/02/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 22/02/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 17/02/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 14/02/2023 |
Work in progress | 55% Completed
All pipe line laying work completed. Total 500 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvements to Moorkanad Scheme
Mankada AE |
Date: 10/02/2023 |
Work in progress | 26% Completed
Total 500 FHTCs completed ,out of which 494 FHTC geotagged.
Mankada AE |
Date: 04/02/2023 |
Work in progress | 26% Completed
Total 500 FHTCs completed ,out of which 494 FHTC geotagged.
Mankada AE |
Date: 31/01/2023 |
Work in progress | 26% Completed
Total 500 FHTCs completed ,out of which 494 FHTC geotagged.
Mankada AE |
Date: 24/01/2023 |
Work in progress | 25% Completed
Total 500 FHTCs completed ,out of which 494 FHTC geotagged.
Mankada AE |
Date: 17/01/2023 |
Work in progress | 24% Completed
Total 455 FHTCs completed ,out of which 455 FHTC geotagged.
Mankada AE |
Date: 11/01/2023 |
Work in progress | 24% Completed
Total 455 FHTCs completed ,out of which 455 FHTC geotagged.
Mankada AE |
Date: 07/01/2023 |
Work in progress | 24% Completed
Total 455 FHTCs completed ,out of which 455 FHTC geotagged.
Mankada AE |
Date: 03/01/2023 |
Work in progress | 24% Completed
Total 455 FHTCs completed ,out of which 455 FHTC geotagged.
Mankada AE |
Date: 28/12/2022 |
Work in progress | 24% Completed
Total 455 FHTCs completed ,out of which 455 FHTC geotagged.
Mankada AE |
Date: 21/12/2022 |
Work in progress | 20% Completed
Total 256 FHTCs completed ,out of which 241 FHTC geotagged.
Mankada AE |
Date: 17/12/2022 |
Work in progress | 20% Completed
Total 241 FHTCs completed ,out of which 241 FHTC geotagged.
Mankada AE |
Date: 12/12/2022 |
Work in progress | 17% Completed
Total 160 FHTCs completed ,out of which 40 FHTC geotagged.
Mankada AE |
Date: 25/11/2022 |
Work in progress | 17% Completed
Total 150 FHTCs completed ,out of which 36 FHTC geotagged.
Mankada AE |
Date: 16/11/2022 |
Work in progress | 16% Completed
Total 150 FHTCs completed ,out of which 27 FHTC geotagged.
Mankada AE |
Date: 11/11/2022 |
Work in progress | 16% Completed
Total 150 FHTCs completed ,out of which 27 FHTC geotagged.
Mankada AE |
Date: 05/11/2022 |
Work in progress | 15% Completed
8 km Pipe line work going on. Total 150 FHTCs completed ,out of which 25 FHTC geotagged.
Mankada AE |
Date: 26/10/2022 |
Work in progress | 14% Completed
Total 150 FHTCs completed ,out of which 20 FHTC geotagged.
Mankada AE |
Date: 17/10/2022 |
Work in progress | 14% Completed
Total 150 FHTCs completed ,out of which 15 FHTC geotagged.
Mankada AE |
Date: 07/10/2022 |
Work in progress | 13% Completed
Total 150 FHTCs completed ,out of which 12 FHTC geotagged.
Mankada AE |
Date: 29/09/2022 |
Work in progress | 13% Completed
Total 150 FHTCs completed ,out of which 2 FHTC geotagged.
Mankada AE |
Date: 24/09/2022 |
Work in progress | 12% Completed
Completed laying of 2 km distribution lines and 100 FHTC completed but not geotagged
Mankada AE |
Date: 19/09/2022 |
Work in progress | 11% Completed
Completed laying of 2 km distribution lines and 100 FHTC completed but not geotagged
Mankada AE |
Date: 14/09/2022 |
Work in progress | 10% Completed
Completed laying of 2 km distribution lines and 100 FHTC completed but not geotagged
Mankada AE |
Date: 05/09/2022 |
Work in progress | 10% Completed
Completed laying of 2 km distribution lines and 90 FHTC completed but not geotagged
Mankada AE |
Date: 01/09/2022 |
Work in progress | 10% Completed
Completed laying of 2 km distribution lines and 90 FHTC completed but not geotagged
Mankada AE |
Date: 26/08/2022 |
Work in progress | 10% Completed
Completed laying of 2km distribution lines and 90 FHTC completed but not geotagged
Mankada AE |
Date: 23/08/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 22/08/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 16/08/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 11/08/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 08/08/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 03/08/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 27/07/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 25/07/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 22/07/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 16/07/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 12/07/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 08/07/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 04/07/2022 |
Work in progress | 1% Completed
Pipe laying and trenching works ongoing
Mankada AE |
Date: 01/07/2022 |
Work in progress | 0% Completed
Pipe Laying started
Mankada AE |
Date: 15/06/2022 |
Work in progress | 0% Completed
Pipe supplied
Malappuram PH Dn EE |
Date: 03/06/2022 |
Work in progress | 0% Completed
Agreement executed
Malappuram PH Dn EE |
Date: 11/05/2022 |
Work has started | 0% Completed
Agreement executed
Malappuram PH Dn EE |
Date: 06/05/2022 |
Work has started | 0% Completed
package 4- Agreement executed on 08.04.2022
Malappuram PH Dn EE |
Date: 26/04/2022 |
Work has started | 0% Completed
Agreement to be executed
Malappuram PH Dn EE |
Date: 19/04/2022 |
Work has started | 0% Completed
Reversed work order awarded on 26/03/2022
Malappuram PH Dn EE |
Date: 23/03/2022 |
Work has started | 0% Completed
work cancelled retender invited.
Malappuram PH Dn EE |
Date: 14/03/2022 |
Work has started | 0% Completed
work cancelled retender invited.
Malappuram PH Dn EE |
Date: 25/02/2022 |
Work has started | 0% Completed
Agmt not executed. letter given to 2nd lowest
Malappuram PH Dn EE |
Date: 18/02/2022 |
Work has started | 0% Completed
Work order issued on 15.01.2022