Project | JJM-Phase 2-Providing remaining FTHC in Mankada pt from the scheme CARWSS to Moorkanad and adjoining villages.-Package IV |
---|---|
Project Code | MLPJJM09218974P4 |
Type | Package |
Main Project | JJM-Phase 2-2021-2022 -Providing remaining FTHC in Mankada pt from the scheme CARWSS to Moorkanad and adjoining villages. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Package IV - 870 FHTCs |
Status | On-going |
District | Malappuram |
Executing Office | Mankada PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 25000000 |
TS Number | Reg.No.16099/2021-2022 |
Technical specification | The project includes providing 870 FHTCs to various places in Mankada Panchayath |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 08/04/2022 |
---|---|
Scheduled date of Completion as per agreement | 19 Sep 2022 |
Expected date of Completion | 24/03/2023 |
TS Date | 23 Dec 2021 |
---|---|
Estimate Approval | 15 Dec 2021 |
NIT Approval | 23 Dec 2021 |
Tender Closing | 18 Mar 2022 |
Technichal Pre-Qualification | 22 Mar 2022 |
Price bid opening | 22 Mar 2022 |
Workorder Date | 26 Mar 2022 |
---|---|
NA | 08 Apr 2022 |
Mankada AE |
Date: 12/08/2023 |
Work has been completed | 100% Completed
All pipe line laying work completed. The work includes 870 nos of FHTC, out of this 623 FHTC has been completed. The remaining 247 nos of FHTCs can be provided only after completion of the ongoing pipe laying work of Project Division, Malappuram. JJM Phase 2 package 5 is ongoing work and if there is any further demand for FHTCs from consumer side, it can be completed under package 5. Hence considering the the above facts package 4 under JJM Phase II may be considered as completed..
Mankada AE |
Date: 09/08/2023 |
Work in progress | 56% Completed
All pipe line laying work completed. Total 591 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement.