JJM-Phase 2-Providing remaining FTHC in Mankada pt from the scheme CARWSS to Moorkanad and adjoining villages.-Package IV

Project JJM-Phase 2-Providing remaining FTHC in Mankada pt from the scheme CARWSS to Moorkanad and adjoining villages.-Package IV
Project Code MLPJJM09218974P4
Type Package
Main Project JJM-Phase 2-2021-2022 -Providing remaining FTHC in Mankada pt from the scheme CARWSS to Moorkanad and adjoining villages.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Package IV - 870 FHTCs
Status On-going
District Malappuram
Executing Office Mankada PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 25000000
TS Number Reg.No.16099/2021-2022
Technical specification The project includes providing 870 FHTCs to various places in Mankada Panchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/04/2022
Scheduled date of Completion as per agreement 19 Sep 2022
Expected date of Completion 24/03/2023

Processing Dates

TS Date 23 Dec 2021
Estimate Approval 15 Dec 2021
NIT Approval 23 Dec 2021
Tender Closing 18 Mar 2022
Technichal Pre-Qualification 22 Mar 2022
Price bid opening 22 Mar 2022

Approval Dates

Workorder Date 26 Mar 2022
NA 08 Apr 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mankada AE
Date: 12/08/2023

Work has been completed | 100% Completed

All pipe line laying work completed. The work includes 870 nos of FHTC, out of this 623 FHTC has been completed. The remaining 247 nos of FHTCs can be provided only after completion of the ongoing pipe laying work of Project Division, Malappuram. JJM Phase 2 package 5 is ongoing work and if there is any further demand for FHTCs from consumer side, it can be completed under package 5. Hence considering the the above facts package 4 under JJM Phase II may be considered as completed..

Mankada AE
Date: 09/08/2023

Work in progress | 56% Completed

All pipe line laying work completed. Total 591 FHTCs given. Further FHTCs can be given along with project division ongoing pipeline work associated with Improvement.