Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kottiyam PH Sn AE
Date: 04/02/2025

Work has been completed | 100% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying , interconnection work and valve fixing completed. Chlorination arrangement fixed. Electrical Panel board fixed. Scouring completed.Black granite stone slab with carving letters fixed. Inaguration done by Hon. MLA P.C. Vishnunath on 01/02/2025. Work Completed.

Kottiyam PH Sn AE
Date: 01/02/2025

Work in progress | 95% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying , interconnection work and valve fixing completed. Chlorination arrangement fixed. Electrical Panel board fixed. Scouring completed.Black granite stone slab with carving letters fixed. Trial run ongoing.

Kottiyam PH Sn AE
Date: 29/01/2025

Work in progress | 90% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying , interconnection work and valve fixing completed. Chlorination arrangement fixed. Electrical Panel board fixed. Scouring completed.Black granite stone slab with carving letters fixed.

Kottiyam PH Sn AE
Date: 25/01/2025

Work in progress | 80% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying , interconnection work and valve fixing completed. Chlorination arrangement fixed. Electrical Panel board fixed. Scouring ongoing.

Kottiyam PH Sn AE
Date: 23/01/2025

Work in progress | 80% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying , interconnection work and valve fixing completed. Chlorination arrangement fixed. Electrical Panel board fixed. Scouring ongoing.

Kottiyam PH Sn AE
Date: 20/01/2025

Work in progress | 75% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying , interconnection work and valve fixing completed. Chlorination arrangement fixed.

Kottiyam PH Sn AE
Date: 18/01/2025

Work in progress | 75% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying , interconnection work and valve fixing completed. Chlorination arrangement fixed.

Kottiyam PH Sn AE
Date: 15/01/2025

Work in progress | 70% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying for interconnection work ongoing.

Kottiyam PH Sn AE
Date: 13/01/2025

Work in progress | 70% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. Pipe laying 110mm upvc for interconnection work in progress

Kottiyam PH Sn AE
Date: 10/01/2025

Work in progress | 60% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected.

Kottiyam PH Sn AE
Date: 09/01/2025

Work in progress | 60% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected.

Kottiyam PH Sn AE
Date: 06/01/2025

Work in progress | 50% Completed

work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received

Kottiyam PH Sn AE
Date: 04/01/2025

Work in progress | 50% Completed

Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. Waiting for power supply.