| Project | MLA SDF RWSS to Thrikovilvattom MLA SDF 2024 25 Honorable MLA Sri P C Vishnunath Thrikovilvattom Grama Panchayath Construction of pump house and commissioning of tube well and allied works at Kottamuri Vayal in Ward no19 of Thrikovilvattom Panchayath. |
|---|---|
| Project Code | KLMDEPO092416996P1 |
| Type | Package |
| Main Project | MLA SDF RWSS to Thrikovilvattom MLA SDF 2024 25 Honorable MLA Sri P C Vishnunath Thrikovilvattom Grama Panchayath Construction of pump house and commissioning of tube well and allied works at Kottamuri Vayal in Ward no19 of Thrikovilvattom Panchayath. |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | MLA SDF RWSS to Thrikovilvattom MLA SDF 2024 25 Honorable MLA Sri P C Vishnunath Thrikovilvattom Grama Panchayath Construction of pump house and commissioning of tube well and allied works at Kottamuri Vayal in Ward no19 of Thrikovilvattom Panchayath. |
| Status | On-going |
| District | Kollam |
| Executing Office | Kottiyam PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 990000 |
| TS Number | 13166/2024-2025 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 02/11/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 22 Jan 2024 |
| Expected date of Completion | 09/01/2025 |
| TS Date | 12 Sep 2024 |
|---|---|
| Estimate Approval | 12 Sep 2024 |
| NIT Approval | 10 Oct 2024 |
| Tender Closing | 30 Sep 2024 |
| Price bid opening | 01 Oct 2024 |
| Workorder Date | 10 Oct 2024 |
|---|---|
| NA | 23 Oct 2024 |
| Kottiyam PH Sn AE |
| Date: 04/02/2025 |
Work has been completed | 100% Completed
Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying , interconnection work and valve fixing completed. Chlorination arrangement fixed. Electrical Panel board fixed. Scouring completed.Black granite stone slab with carving letters fixed. Inaguration done by Hon. MLA P.C. Vishnunath on 01/02/2025. Work Completed..
| Kottiyam PH Sn AE |
| Date: 01/02/2025 |
Work in progress | 95% Completed
Work started on 22.11.2024. Construction of operator room,BP stacking room and tank fixing base completed. DN from KSEB received and paid. KSEB Connection received. Bore Development Completed.Submerssible Pump errected. 110mm upvc pipe laying , interconnection work and valve fixing completed. Chlorination arrangement fixed. Electrical Panel board fixed. Scouring completed.Black granite stone slab with carving letters fixed. Trial run ongoing..