All updates

Sasthamcotta WS Sn 2 HW - AE
Date: 02/07/2024

Work in progress | 22% Completed

Filter Bed No.6 all items of work completed .Work in 5 th filter bed in progress.

Sasthamcotta WS Sn 2 HW - AE
Date: 29/06/2024

Work in progress | 22% Completed

Filter Bed No.6 all items of work completed .Work in 5 th filter bed in progress.

Sasthamcotta WS Sn 2 HW - AE
Date: 25/06/2024

Work in progress | 22% Completed

Filter Bed No.6 all items of work completed .Work in 5 th filter bed in progress.

Attached images

img

Sasthamcotta WS Sub-Dn - AEE
Date: 20/06/2024

Work in progress | 20% Completed

Filter Bed No.6 all items of work completed and bill submitted.