Jal Jeevan Mission (JJM)-JJM West kallada-JJM West kallada: Replacement of filter bed of 37.5 MLD treatment plant and paving tiles inside the filter bed.-General Civil Work

Project Jal Jeevan Mission (JJM)-JJM West kallada-JJM West kallada: Replacement of filter bed of 37.5 MLD treatment plant and paving tiles inside the filter bed.-General Civil Work
Project Code KLMJJM082016006P1
Type Package
Main Project Jal Jeevan Mission (JJM)-JJM West kallada-JJM West kallada: Replacement of filter bed of 37.5 MLD treatment plant and paving tiles inside the filter bed.-General Civil Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM West kallada-JJM West kallada: Replacement of filter bed of 37.5 MLD treatment plant and paving tiles inside the filter bed.-General Civil Work
Status On-going
District Kollam
Executing Office Sasthamcottah WS Sn2
Agreement Number
Agreement Date
TS Amount (Rs) 5391811
TS Number 8859/2023-2024
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 15 Jul 2023

Approval Dates

Workorder Date 27 Nov 2023
NA 14 Dec 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sasthamcotta WS Sn 2 HW - AE
Date: 02/07/2024

Work in progress | 22% Completed

Filter Bed No.6 all items of work completed .Work in 5 th filter bed in progress..

Sasthamcotta WS Sn 2 HW - AE
Date: 29/06/2024

Work in progress | 22% Completed

Filter Bed No.6 all items of work completed .Work in 5 th filter bed in progress..