Kottiyam PH Sn AE
Date: 12/07/2024

Work has been completed | 100% Completed

Honorable MLA Shri P.C Vishnunath inaugurated the pump house today, marking the occasion with the commencement of water pumping into the line. The final bill has been submitted, and the work has been completed.

Kottiyam PH Sn AE
Date: 10/07/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 05/07/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 01/07/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 26/06/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 24/06/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 18/06/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 13/06/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 10/06/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 07/06/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 03/06/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 31/05/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 27/05/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 21/05/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 17/05/2024

Work in progress | 99% Completed

Trial Run ongoing

Kottiyam PH Sn AE
Date: 13/05/2024

Work in progress | 99% Completed

Trial Run.

Kottiyam PH Sn AE
Date: 11/05/2024

Work in progress | 97% Completed

Road restoration work completed.

Kottiyam PH Sn AE
Date: 10/05/2024

Work in progress | 95% Completed

Interconnection of newly laid line with existing pvc pipe line. All Electrical and Automation work completed.

Kottiyam PH Sn AE
Date: 08/05/2024

Work in progress | 91% Completed

Pump control room, disinfectant stacking room and Bleaching powder tank fixing base roof work and plastering work ongoing

Kottiyam PH Sn AE
Date: 07/05/2024

Work in progress | 91% Completed

Pump control room, disinfectant stacking room and Bleaching powder tank fixing base purlin fixing ongoing

Kottiyam PH Sn AE
Date: 06/05/2024

Work in progress | 91% Completed

Pump control room, disinfectant stacking room and Bleaching powder tank fixing base side covering with corrugated sheet ongoing

Kottiyam PH Sn AE
Date: 04/05/2024

Work in progress | 91% Completed

Pump control room, disinfectant stacking room and Bleaching powder tank fixing base completed upto plinth level.

Kottiyam PH Sn AE
Date: 30/04/2024

Work in progress | 90% Completed

KSEB connection received and pump set errected

Kottiyam PH Sn AE
Date: 27/04/2024

Work in progress | 90% Completed

KSEB connection received and pump set errected

Kottiyam PH Sn AE
Date: 23/04/2024

Work in progress | 90% Completed

KSEB connection received and pump set errected

Kottiyam PH Sn AE
Date: 19/04/2024

Work in progress | 90% Completed

KSEB connection received and pump set errected

Kottiyam PH Sn AE
Date: 15/04/2024

Work in progress | 50% Completed

Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing

Kottiyam PH Sn AE
Date: 09/04/2024

Work in progress | 50% Completed

Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing

Kottiyam PH Sn AE
Date: 02/04/2024

Work in progress | 50% Completed

Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing

Kottiyam PH Sn AE
Date: 30/03/2024

Work in progress | 50% Completed

Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing

Kottiyam PH Sn AE
Date: 26/03/2024

Work in progress | 50% Completed

Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing

Kottiyam PH Sn AE
Date: 20/03/2024

Work in progress | 50% Completed

Operator room building completed, Chlorine stacking room completed, Chlorine tank stand completed. Panel board errection completed. Electrical connection procedure from KSEB ongoing

Kollam PH Dn EE
Date: 14/03/2024

Work has started | 0% Completed

LoA issued on 04.03.2024. Agreement to be executed