MLA-SDF-2023-24- Hon’ble MLA Sri.P.C.Vishnunath - Kottamkara Grama Panchayath -Construction of pumphouse at Melevila Ward no. 18 and commissioning of tubewell and allied works at Melevila pump house in Kottamkara Panchayath

Project MLA-SDF-2023-24- Hon’ble MLA Sri.P.C.Vishnunath - Kottamkara Grama Panchayath -Construction of pumphouse at Melevila Ward no. 18 and commissioning of tubewell and allied works at Melevila pump house in Kottamkara Panchayath
Project Code KLMDC-LAC/ADS/SDF/KSCADC022415739P1
Type Package
Main Project MLA-SDF-2023-24- Hon’ble MLA Sri.P.C.Vishnunath - Kottamkara Grama Panchayath -Construction of pumphouse at Melevila Ward no. 18 and commissioning of tubewell and allied works at Melevila pump house in Kottamkara Panchayath
Funding Agency DC-LAC/ADS/SDF/KSCADC
Category MLA SDF
Type of scheme Water Supply
Scheme DC-LAC/ADS/SDF/KSCADC
Description MLA-SDF-2023-24- Hon’ble MLA Sri.P.C.Vishnunath - Kottamkara Grama Panchayath -Construction of pumphouse at Melevila Ward no. 18 and commissioning of tubewell and allied works at Melevila pump house in Kottamkara Panchayath
Status On-going
District Kollam
Executing Office Kottiyam PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 760000
TS Number 27545/2023-2024
Technical specification Commissioning of tube well with Submersible Pump set with 80m head and 250LPM discharge and allied works including chlorination arrangements.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/02/2024
Scheduled date of Completion as per agreement 30 Jun 2024
Expected date of Completion 11/05/2024

Processing Dates

TS Date 15 Feb 2024
Estimate Approval 16 Feb 2024
NIT Approval 16 Feb 2024
Tender Closing 23 Feb 2024
Technichal Pre-Qualification 24 Feb 2024
Price bid opening 24 Feb 2024

Approval Dates

Workorder Date 04 Mar 2024
NA 15 Mar 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottiyam PH Sn AE
Date: 12/07/2024

Work has been completed | 100% Completed

Honorable MLA Shri P.C Vishnunath inaugurated the pump house today, marking the occasion with the commencement of water pumping into the line. The final bill has been submitted, and the work has been completed. .

Kottiyam PH Sn AE
Date: 10/07/2024

Work in progress | 99% Completed

Trial Run ongoing.