| Project | MLA-SDF-2023-24- Hon’ble MLA Sri.P.C.Vishnunath - Kottamkara Grama Panchayath -Construction of pumphouse at Melevila Ward no. 18 and commissioning of tubewell and allied works at Melevila pump house in Kottamkara Panchayath |
|---|---|
| Project Code | KLMDC-LAC/ADS/SDF/KSCADC022415739P1 |
| Type | Package |
| Main Project | MLA-SDF-2023-24- Hon’ble MLA Sri.P.C.Vishnunath - Kottamkara Grama Panchayath -Construction of pumphouse at Melevila Ward no. 18 and commissioning of tubewell and allied works at Melevila pump house in Kottamkara Panchayath |
| Funding Agency | DC-LAC/ADS/SDF/KSCADC |
| Category | MLA SDF |
| Type of scheme | Water Supply |
| Scheme | DC-LAC/ADS/SDF/KSCADC |
| Description | MLA-SDF-2023-24- Hon’ble MLA Sri.P.C.Vishnunath - Kottamkara Grama Panchayath -Construction of pumphouse at Melevila Ward no. 18 and commissioning of tubewell and allied works at Melevila pump house in Kottamkara Panchayath |
| Status | On-going |
| District | Kollam |
| Executing Office | Kottiyam PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 760000 |
| TS Number | 27545/2023-2024 |
| Technical specification | Commissioning of tube well with Submersible Pump set with 80m head and 250LPM discharge and allied works including chlorination arrangements. |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 12/02/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Jun 2024 |
| Expected date of Completion | 11/05/2024 |
| TS Date | 15 Feb 2024 |
|---|---|
| Estimate Approval | 16 Feb 2024 |
| NIT Approval | 16 Feb 2024 |
| Tender Closing | 23 Feb 2024 |
| Technichal Pre-Qualification | 24 Feb 2024 |
| Price bid opening | 24 Feb 2024 |
| Workorder Date | 04 Mar 2024 |
|---|---|
| NA | 15 Mar 2024 |
| Kottiyam PH Sn AE |
| Date: 12/07/2024 |
Work has been completed | 100% Completed
Honorable MLA Shri P.C Vishnunath inaugurated the pump house today, marking the occasion with the commencement of water pumping into the line. The final bill has been submitted, and the work has been completed. .
| Kottiyam PH Sn AE |
| Date: 10/07/2024 |
Work in progress | 99% Completed
Trial Run ongoing.