Palakkad Project Dn AE 4
Date: 22/06/2024

Work in progress | 23% Completed

Total laid so far = 3.987/11km.Interconnection work and restoration work on going.

Palakkad Project Dn AE 4
Date: 21/06/2024

Work in progress | 23% Completed

Total laid so far = 3.366/11km.Interconnection work and restoration work on going.

Palakkad Project Dn AE 4
Date: 15/06/2024

Work in progress | 23% Completed

Total laid so far = 3.366/11km.Interconnection work and restoration work on going.

Palakkad Proj Dn AE 4
Date: 04/06/2024

Work in progress | 20% Completed

Total laid so far 90 mm UPVC = 2.837 kms. Vaniamkulam - kothakkurssi road btw ( n16 n17 ) near pathamkulam puthuvayil colony road 90 mm UPVC class - 3/6 kg pipe = 42 m 80 mm GI pipe ( Culvert crossing ) = 6 m

Palakkad Proj Dn AE 4
Date: 27/05/2024

Work in progress | 17% Completed

2.795 Km laid so far ,90 mm UPVC pipe. Interconnections work on going.

Palakkad Proj Dn AE 4
Date: 20/05/2024

Work in progress | 16% Completed

2.795 Km laid so far ,90 mm UPVC pipe. Interconnections work on going.

Palakkad Proj Dn AE 4
Date: 13/05/2024

Work in progress | 16% Completed

2.795 Km laid so far ,90 mm UPVC pipe. Interconnections work on going.

Palakkad Project Dn AE 4
Date: 08/05/2024

Work in progress | 16% Completed

Total laid so far 90 mm UPVC pipe = 2795 m.90 mm HDPE to 80 mm GI interconnections work at panamanna palli.

Palakkad Project Dn AE 4
Date: 06/05/2024

Work in progress | 16% Completed

Total laid so far 90 mm UPVC pipe = 2795 m.90 mm HDPE to 80 mm GI interconnections work at panamanna palli.

Palakkad Project Dn AE 4
Date: 04/05/2024

Work in progress | 16% Completed

Total laid so far 90 mm UPVC pipe = 2795 m.90 mm HDPE to 80 mm GI interconnections work at panamanna palli.

Palakkad Project Dn AE 4
Date: 02/05/2024

Work in progress | 15% Completed

Total laid so far 90 mm UPVC pipe = 2795 m.Kottakulam - Anthoorparamb road btw ( n478 n584 ) at puthanveed road kottakulam 90 mm UPVC class-3/6 kg interconnection gap = 8 m Pavukkonam road btw ( n726 n743 ) at Cholayil road Pavukkonam 90 mm UPVC class-3/6 kg interconnection gap = 3 m Kothakkurssi - Vaniamkulam road btw ( n291 n294 ) opposite road of PKM store pathamkulam 90 mm UPVC class-3/6 kg interconnection gap = 3 m

Palakkad Project Dn AE 4
Date: 30/04/2024

Work in progress | 14% Completed

Total laid so far 90 mm UPVC = 2727 m.Kothakkurssi - Vaniamkulam roadb/w ( n100 n586 ) at Ezhupothiyil road Theyyampadi90 mm UPVC class -3/6 kg pipe = 87 m Pathamkulam - Kottakulam road b/w ( n446 n55 ) at Uppilakattil road kottakulam90 mm UPVC class -3/6 kg pipe = 56 mAnthoorparamb roadb/w ( n440 n442 ) Interconnection gap 90 mm UPVC class -3/6 kg pipeKottakulam road = 4 mVadakkepeedikakkal road = 11 m

Palakkad Project Dn AE 4
Date: 16/04/2024

Work in progress | 12% Completed

Total laid so far 90 mm UPVC = 2080 m Anthoorparamb road b/w ( n440 n442 ) at kottakulam road 90 mm UPVC class-3/6kg pipe = 66 m

Palakkad Project Dn AE 4
Date: 15/04/2024

Work in progress | 10% Completed

Total laid so far 90 mm UPVC = 2014 m Anthoorparamb road b/w ( n440 n442 ) at vadakkepeedikakkal road 90 mm UPVC class-3/6kg pipe = 126 m Yaarampadi - Edakkode road b/w ( n678 n679 ) at palakkal road 90 mm UPVC class-3/6kg pipe = 36 m Kothakkurssi - Vaniamkulam road b/w ( n98 n100 ) opposite palakkode road at Theyyampadi 90 mm UPVC class-3/6kg pipe = 36 m

Palakkad Project Dn AE 4
Date: 12/04/2024

Work in progress | 10% Completed

Total laid so far 90 mm UPVC = 1816 m Yaarampadi- Edakkode road b/w ( n678 n 679 ) opposite yaarampadi turf 90 mm UPVC class-3/6kg pipe = 72 m Kottakulam- Anthoorparamb road b/w ( n478 n584 ) at puthanveed road kottakulam 90 mm UPVC class-3/6kg pipe = 72 m

Palakkad Project Dn AE 4
Date: 11/04/2024

Work in progress | 10% Completed

Total laid so far 90 mm UPVC = 1672 m. Palakkode - Kanjiram colony road b/w ( n790 n1 ) at kavukundil road 90 mm UPVC class-3/6kg pipe = 84 m Kothakkurssi - Vaniamkulam road b/w ( n132 n424 ) at Thekkappattu mana road Althara 90 mm UPVC class-3/6kg pipe = 78 m

Palakkad Project Dn AE 4
Date: 09/04/2024

Work in progress | 10% Completed

Palakkode - Kanjiram colony road b/w ( n790 n1 ) at kavukundil road 90 mm UPVC class-3/6kg pipe = 63 m Kothakkurssi - Vaniamkulam road b/w ( n291 n294 ) opposite road of PKM store pathamkulam 90 mm UPVC class-3/6kg pipe = 102 m Total laid so far 90 mm UPVC = 1510 m

Palakkad Project Dn AE 4
Date: 08/04/2024

Work in progress | 5% Completed

Vaniamkulam - kothakkurssi road b/w ( n165 n804 ) at Palakkode Kallamparamb canal road 90 mm UPVC class-3/6kg pipe = 132 m Total laid so far 90 mm UPVC = 1345 m

Palakkad Project Dn AE 4
Date: 11/03/2024

Work in progress | 3% Completed

Vaniamkulam - kothakkurssi Rd b/w ( n16 n17 ) near pathamkulam puthuvayil colony mud Rd 90 mm UPVC class-3/6kg pipe = 78 m Vaniamkulam - kothakkurssi road b/w ( n165 n804 ) near palakkode mundokkalam colony mud Rd 90 mm UPVC class-3/6kg pipe = 78 m Total laid so far 90 mm UPVC = 1380 m

Palakkad Project Dn AE 4
Date: 09/03/2024

Work in progress | 2% Completed

Pathamkulam - Ambalavattam road b/w ( n718 n741 ) near villinamkunnu puthanpariyarath mud road 90 mm UPVC class -3/6kg pipe = 126 m Pathamkulam - Ambalavattam road b/w ( n741 n719 ) mud road near vellinamkunnu colony 90 mm UPVC class-3/6kg pipe = 120 m Total laid so far 90 mm UPVC = 1152 m

Palakkad Project Dn AE 4
Date: 08/03/2024

Work in progress | 2% Completed

Total laid so far 90 mm UPVC = 906 m Pathamkulam - Ambalavattam road b/w ( n718 n741 ) near villinamkunnu puthanpariyarath road 90 mm UPVC class -3/6kg pipe = 168 m Pathamkulam - Ambalavattam road b/w ( n718 n741 ) near vellinamkunnu colony 90 mm UPVC class-3/6kg pipe = 138 m

Palakkad Project Dn AE 4
Date: 07/03/2024

Work in progress | 2% Completed

Total laid so far 90 mm UPVC = 600 m Pathamkulam - Ambalavattam road b/w ( n341 n253 ) near padikkaparambil road 90 mm UPVC class-3/6kg pipe = 138 m Ambalavattam - Vattaparambu road b/w ( n365 n590 ) near Alangattupadi road 90 mm UPVC class-3/6kg pipe = 102 m Panamanna - Ambalavattam road b/w ( n722 n361 ) 90 mm UPVC class-3/6kg pipe = 30 m

Palakkad Project Dn AE 4
Date: 06/03/2024

Work in progress | 2% Completed

UPVC class-3/6kg pipe = 210 m Panamanna - Ambalavattom road ration shop junction b/w ( n107 n511 ) by the side of ponnu ettan's stationary mud road 90 mm UPVC class-3/6kg pipe = 120 m Panamanna - Ambalavattom road b/w ( n722 n361 ) by the side of JS steels mud road

Palakkad Project Dn AE 4
Date: 02/03/2024

Work in progress | 1% Completed

Supplied 3504 nos of 90MM 6 KG AIZAR ISI - 6 MTR.