Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

(JJM) - WSS to Ananganadi Grama Panchayath - Additional works

Project (JJM) - WSS to Ananganadi Grama Panchayath - Additional works
Project Code PKDJJM102315827P2
Type Package
Main Project JJM - WSS to Ananganadi Grama Panchayath - Additional works.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description (JJM) - WSS to Ananganadi Grama Panchayath - Additional works - Pipe Line Extension to Uncovered areas and LSGD Road Restoration work
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 19000000
TS Number CE(NR)/EST_TS/25907/2023
Technical specification Pipe Line Extension to Uncovered areas and LSGD Road Restoration work . Supply of PVC Pipe,6kg/cum2 ,90mm Dia - 7000m Providing and fixing G.I pipes complete with GI fittings including trenching and refilling etc... - 4000 m

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/01/2024
Scheduled date of Completion as per agreement 22 Jul 2024
Expected date of Completion 22/07/2024

Processing Dates

TS Date 25 Nov 2023
Estimate Approval 25 Nov 2024
NIT Approval 20 Dec 2023
Tender Closing 29 Dec 2023
Price bid opening 30 Dec 2023

Approval Dates

Workorder Date 12 Jan 2024
NA 23 Jan 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Project Dn AE 4
Date: 22/06/2024

Work in progress | 23% Completed

Total laid so far = 3.987/11km.Interconnection work and restoration work on going..

Palakkad Project Dn AE 4
Date: 21/06/2024

Work in progress | 23% Completed

Total laid so far = 3.366/11km.Interconnection work and restoration work on going..