Project | (JJM) - WSS to Ananganadi Grama Panchayath - Additional works |
---|---|
Project Code | PKDJJM102315827P2 |
Type | Package |
Main Project | JJM - WSS to Ananganadi Grama Panchayath - Additional works. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | (JJM) - WSS to Ananganadi Grama Panchayath - Additional works - Pipe Line Extension to Uncovered areas and LSGD Road Restoration work |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 19000000 |
TS Number | CE(NR)/EST_TS/25907/2023 |
Technical specification | Pipe Line Extension to Uncovered areas and LSGD Road Restoration work . Supply of PVC Pipe,6kg/cum2 ,90mm Dia - 7000m Providing and fixing G.I pipes complete with GI fittings including trenching and refilling etc... - 4000 m |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 12/01/2024 |
---|---|
Scheduled date of Completion as per agreement | 22 Jul 2024 |
Expected date of Completion | 22/07/2024 |
TS Date | 25 Nov 2023 |
---|---|
Estimate Approval | 25 Nov 2024 |
NIT Approval | 20 Dec 2023 |
Tender Closing | 29 Dec 2023 |
Price bid opening | 30 Dec 2023 |
Workorder Date | 12 Jan 2024 |
---|---|
NA | 23 Jan 2024 |
Palakkad Project Dn AE 4 |
Date: 22/06/2024 |
Work in progress | 23% Completed
Total laid so far = 3.987/11km.Interconnection work and restoration work on going..
Palakkad Project Dn AE 4 |
Date: 21/06/2024 |
Work in progress | 23% Completed
Total laid so far = 3.366/11km.Interconnection work and restoration work on going..