| Punalur WS Sn - AE |
| Date: 25/10/2023 |
Work has been completed | 100% Completed
Work has been completed
| Punalur WS Sn - AE |
| Date: 19/10/2023 |
Work in progress | 90% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 16/10/2023 |
Work in progress | 85% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 11/10/2023 |
Work in progress | 80% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 07/10/2023 |
Work in progress | 72% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 06/10/2023 |
Work in progress | 58% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 03/10/2023 |
Work in progress | 58% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 29/09/2023 |
Work in progress | 57% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 25/09/2023 |
Work in progress | 56% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 18/09/2023 |
Work in progress | 55% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 15/09/2023 |
Work in progress | 53% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 11/09/2023 |
Work in progress | 52% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 05/09/2023 |
Work in progress | 51% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 02/09/2023 |
Work in progress | 51% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 25/08/2023 |
Work in progress | 51% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 21/08/2023 |
Work in progress | 51% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 17/08/2023 |
Work in progress | 50% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 14/08/2023 |
Work in progress | 49% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 11/08/2023 |
Work in progress | 48% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 08/08/2023 |
Work in progress | 47% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 03/08/2023 |
Work in progress | 46% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 31/07/2023 |
Work in progress | 44% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 27/07/2023 |
Work in progress | 43% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 24/07/2023 |
Work in progress | 43% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 19/07/2023 |
Work in progress | 43% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 14/07/2023 |
Work in progress | 43% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 10/07/2023 |
Work in progress | 42% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 04/07/2023 |
Work in progress | 42% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 30/06/2023 |
Work in progress | 42% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 27/06/2023 |
Work in progress | 42% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 24/06/2023 |
Work in progress | 42% Completed
Work in progress
| Kottarakkara PH Dn EE |
| Date: 20/06/2023 |
Work in progress | 42% Completed
Construction of tank & pipe line works ongoing
| Punalur WS Sn - AE |
| Date: 16/06/2023 |
Work in progress | 42% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 12/06/2023 |
Work in progress | 41% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 09/06/2023 |
Work in progress | 41% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 06/06/2023 |
Work in progress | 40% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 03/06/2023 |
Work in progress | 40% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 31/05/2023 |
Work in progress | 39% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 27/05/2023 |
Work in progress | 38% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 23/05/2023 |
Work in progress | 37% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 20/05/2023 |
Work in progress | 37% Completed
Work in progress
| Punalur WS Sn - AE |
| Date: 15/05/2023 |
Work in progress | 36% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 11/05/2023 |
| Punalur WS Sn - AE |
| Date: 08/05/2023 |
Work in progress | 36% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 05/05/2023 |
Work in progress | 35% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 02/05/2023 |
Work in progress | 35% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 29/04/2023 |
Work in progress | 30% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 27/04/2023 |
Work in progress | 30% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 24/04/2023 |
Work in progress | 27% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 20/04/2023 |
Work in progress | 25% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 17/04/2023 |
Work in progress | 25% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 13/04/2023 |
Work in progress | 25% Completed
Pumping and distribution line laying in progress. Construction of OHSR started.
| Punalur WS Sn - AE |
| Date: 10/04/2023 |
Work in progress | 25% Completed
Pumping and distribution line laying in progress. Construction of OHSR started.
| Punalur WS Sn - AE |
| Date: 04/04/2023 |
Work in progress | 25% Completed
Pumping and distribution line laying in progress. Construction of OHSR started
| Punalur WS Sn - AE |
| Date: 31/03/2023 |
| Punalur WS Sn - AE |
| Date: 27/03/2023 |
Work in progress | 15% Completed
Pumping and distribution line laying in progress.
| Punalur WS Sn - AE |
| Date: 22/03/2023 |
Work in progress | 15% Completed
Pumping and distribution line laying in progress.
| Punalur WS Sn - AE |
| Date: 18/03/2023 |
Work in progress | 15% Completed
Pumping and distribution line laying in progress.
| Punalur WS Sn - AE |
| Date: 14/03/2023 |
Work in progress | 15% Completed
Pumping and distribution line laying in progress.
| Punalur WS Sn - AE |
| Date: 10/03/2023 |
Work in progress | 15% Completed
Pumping and distribution line laying in progress.
| Punalur WS Sn - AE |
| Date: 09/03/2023 |
Work in progress | 15% Completed
Pumping and distribution line laying in progress.
| Kottarakkara PH Dn EE |
| Date: 08/03/2023 |
Work has started | 0% Completed
Work awarded