| Project | Deposit work- Kollam Jilla Panchayath - Construction of OHSR at Urukunnu |
|---|---|
| Project Code | KLMDEPO012313701P1 |
| Type | Package |
| Main Project | Deposit work- Kollam Jilla Panchayath - Construction of OHSR at Urukunnu |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | Construction of OHSR at Urukunnu |
| Status | Completed |
| District | Kollam |
| Executing Office | Punalur WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 11210000 |
| TS Number | 7314/2022-23 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 24/11/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 29 Nov 2023 |
| Expected date of Completion | Date is not specified |
| TS Date | 15 Jun 2022 |
|---|---|
| Estimate Approval | 15 Jun 2022 |
| Workorder Date | 11 Nov 2022 |
|---|---|
| NA | 30 Nov 2022 |
| Punalur WS Sn - AE |
| Date: 25/10/2023 |
Work has been completed | 100% Completed
Work has been completed.
| Punalur WS Sn - AE |
| Date: 19/10/2023 |
Work in progress | 90% Completed
Work in progress.