Kollam Project HD |
Date: 02/03/2021 |
Work has been completed | 100% Completed
Works completed.
Kollam Project HD |
Date: 27/02/2021 |
Work in progress | 96% Completed
laying works completed, Interconnection and road restoration works in progress
Kollam Project HD |
Date: 26/02/2021 |
Work in progress | 93% Completed
Interconnection and road restoration works in progress
Kollam Project HD |
Date: 24/02/2021 |
Work in progress | 92% Completed
Interconnection and road restoration works in progress
Kollam Project HD |
Date: 22/02/2021 |
Work in progress | 90% Completed
Interconnection and road restoration works in progress
Kollam Project HD |
Date: 19/02/2021 |
Work in progress | 86% Completed
Interconnection and road restoration works in progress
Kollam Project HD |
Date: 18/02/2021 |
Work in progress | 86% Completed
Interconnection and road restoration works in progress
Kollam Project HD |
Date: 15/02/2021 |
Work in progress | 85% Completed
Interconnection and road restoration works in progress
Kollam Project HD |
Date: 09/02/2021 |
Work in progress | 85% Completed
Interconnection and road restoration works in progress
Kollam Project HD |
Date: 05/02/2021 |
Work in progress | 84% Completed
18.347 laid out of 21.63km ,hydrotesting .road restoration in progress.
Kollam Project HD |
Date: 02/02/2021 |
Work in progress | 84% Completed
18.2km laid out of 21.63km .interconnection ,hydrotesting and road restoration in progress
Kollam Project HD |
Date: 31/01/2021 |
Work in progress | 80% Completed
17.4km laid out of 21.63km,hydrotesting ,interconnection and road restoration in progress
Kollam Project HD |
Date: 29/01/2021 |
Work in progress | 80% Completed
17.4km laid out of 21.63km,hydrotesting ,interconnection and road restoration in progress
Kollam Project HD |
Date: 25/01/2021 |
Work in progress | 77% Completed
16.854 km laid out of 21.63km , hydrotesting,interconnection and road restoration works in progress
Kollam Project HD |
Date: 11/01/2021 |
Work in progress | 62% Completed
13.576 km laid out of 21.63km,Hydrotesting ,interconnctions and GI works in progress
Kollam Project HD |
Date: 10/12/2020 |
Work in progress | 31% Completed
8.3km laid out of 26.9km , hydrotesting completed, GI works and road restoration works in progress.
Kollam Project HD |
Date: 19/10/2020 |
Work in progress | 26% Completed
6.97km out of 26.974km laid
Kollam Project HD |
Date: 30/09/2020 |
Work in progress | 24% Completed
5.6 km laid , Hydro testing of pipe line in progress ,GI pipe line works in progress,inter connection works in progress
Kollam Project HD |
Date: 15/08/2020 |
Work in progress | 22% Completed
5.6 km laid , Hydro testing of pipe line in progress ,GI pipe line works in progress,inter connection works in progress.
Kollam Project HD |
Date: 19/06/2020 |
Work in progress | 21% Completed
laying works in progress 5.262kms pipe laid ,8.5km pipe supplied out of 26.974Km
Kollam Project HD |
Date: 18/06/2020 |
Work in progress | 1% Completed
5.262Km pipe laid