Kollam Project HD
Date: 02/03/2021

Work has been completed | 100% Completed

Works completed.

Kollam Project HD
Date: 27/02/2021

Work in progress | 96% Completed

laying works completed, Interconnection and road restoration works in progress

Kollam Project HD
Date: 26/02/2021

Work in progress | 93% Completed

Interconnection and road restoration works in progress

Kollam Project HD
Date: 24/02/2021

Work in progress | 92% Completed

Interconnection and road restoration works in progress

Kollam Project HD
Date: 22/02/2021

Work in progress | 90% Completed

Interconnection and road restoration works in progress

Kollam Project HD
Date: 19/02/2021

Work in progress | 86% Completed

Interconnection and road restoration works in progress

Kollam Project HD
Date: 18/02/2021

Work in progress | 86% Completed

Interconnection and road restoration works in progress

Kollam Project HD
Date: 15/02/2021

Work in progress | 85% Completed

Interconnection and road restoration works in progress

Kollam Project HD
Date: 09/02/2021

Work in progress | 85% Completed

Interconnection and road restoration works in progress

Kollam Project HD
Date: 05/02/2021

Work in progress | 84% Completed

18.347 laid out of 21.63km ,hydrotesting .road restoration in progress.

Kollam Project HD
Date: 02/02/2021

Work in progress | 84% Completed

18.2km laid out of 21.63km .interconnection ,hydrotesting and road restoration in progress

Kollam Project HD
Date: 31/01/2021

Work in progress | 80% Completed

17.4km laid out of 21.63km,hydrotesting ,interconnection and road restoration in progress

Kollam Project HD
Date: 29/01/2021

Work in progress | 80% Completed

17.4km laid out of 21.63km,hydrotesting ,interconnection and road restoration in progress

Kollam Project HD
Date: 25/01/2021

Work in progress | 77% Completed

16.854 km laid out of 21.63km , hydrotesting,interconnection and road restoration works in progress

Kollam Project HD
Date: 11/01/2021

Work in progress | 62% Completed

13.576 km laid out of 21.63km,Hydrotesting ,interconnctions and GI works in progress

Kollam Project HD
Date: 10/12/2020

Work in progress | 31% Completed

8.3km laid out of 26.9km , hydrotesting completed, GI works and road restoration works in progress.

Kollam Project HD
Date: 19/10/2020

Work in progress | 26% Completed

6.97km out of 26.974km laid

Kollam Project HD
Date: 30/09/2020

Work in progress | 24% Completed

5.6 km laid , Hydro testing of pipe line in progress ,GI pipe line works in progress,inter connection works in progress

Kollam Project HD
Date: 15/08/2020

Work in progress | 22% Completed

5.6 km laid , Hydro testing of pipe line in progress ,GI pipe line works in progress,inter connection works in progress.

Kollam Project HD
Date: 19/06/2020

Work in progress | 21% Completed

laying works in progress 5.262kms pipe laid ,8.5km pipe supplied out of 26.974Km

Kollam Project HD
Date: 18/06/2020

Work in progress | 1% Completed

5.262Km pipe laid