Ranni PH Sn - AE
Date: 01/07/2024

Work in progress | 12% Completed

Work ongoing

Ranni PH Sn - AE
Date: 29/06/2024

Work in progress | 10% Completed

FHTC work ongoing

Ranni PH Sub Dn - AEE
Date: 25/06/2024

Work in progress | 10% Completed

FHTC work ongoing

Ranni PH Sub Dn - AEE
Date: 15/06/2024

Work in progress | 10% Completed

FHTC work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 31/05/2024

Work in progress | 10% Completed

Pipe laying and FHTC work ongoing

Attached images

img img img img img img img

Ranni PH Sub Dn - AEE
Date: 30/04/2024

Work in progress | 9% Completed

FHTC & pipe laying work ongoing

Attached images

img img

Ranni PH Sub Dn - AEE
Date: 20/04/2024

Work in progress | 9% Completed

FHTC work ongoing

Attached images

img img img

Ranni PH Sub Dn - AEE
Date: 31/03/2024

Work in progress | 7% Completed

Work slow downed due to non availabilty of 90mm pipes

Attached images

img img

Ranni PH Sub Dn - AEE
Date: 10/02/2024

Work in progress | 6% Completed

Pipe laying work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 03/01/2024

Work in progress | 5% Completed

Pipe laying work & FHTC connections ongoing

Attached images

img img img

Ranni PH Sub Dn - AEE
Date: 29/12/2023

Work in progress | 5% Completed

Pipe laying work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 20/12/2023

Work in progress | 4% Completed

Pipe laying work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 15/12/2023

Work in progress | 4% Completed

Pipe laying work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 09/12/2023

Work in progress | 4% Completed

Pipe laying work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 04/12/2023

Work in progress | 3% Completed

Pipe laying work ongoing

Attached images

img img img img img

Ranni PH Sub Dn - AEE
Date: 30/11/2023

Work in progress | 2% Completed

Pipe laying work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 28/11/2023

Work in progress | 2% Completed

Pipe laying work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 23/11/2023

Work in progress | 2% Completed

Pipe laying work ongoing

Attached images

img img img

Ranni PH Sub Dn - AEE
Date: 18/11/2023

Work in progress | 2% Completed

Pipe laying work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 08/11/2023

Work in progress | 2% Completed

Pipe laying work ongoing

Attached images

img img img

Ranni PH Sub Dn - AEE
Date: 02/11/2023

Work in progress | 2% Completed

Pipe laying work ongoing

Attached images

img img img img

Ranni PH Sub Dn - AEE
Date: 31/10/2023

Work in progress | 1% Completed

90mm PVC pipe laying ongoing

Attached images

img img img img img

Ranni PH Sub Dn - AEE
Date: 28/10/2023

Work in progress | 1% Completed

90mm PVC pipe laying ongoing

Attached images

img img img img img img img

Ranni PH Sub Dn - AEE
Date: 26/10/2023

Work in progress | 1% Completed

Pipe line laying works started

Attached images

img img img