Jal Jeevan Mission (JJM)-JJM : RWSS to Vechoochira Pt:-Laying of pumping/Gravity Mains to Sumps/GLSR/OHSR, providing Distribution Lines and 3950 FHTCs (Vechoochira-1600 nos, Naranamoozhi-350 nos, Pazhavangadi-2000nos) including restoration works of PWD and LSGD Roads-Pipeline Work

Project Jal Jeevan Mission (JJM)-JJM : RWSS to Vechoochira Pt:-Laying of pumping/Gravity Mains to Sumps/GLSR/OHSR, providing Distribution Lines and 3950 FHTCs (Vechoochira-1600 nos, Naranamoozhi-350 nos, Pazhavangadi-2000nos) including restoration works of PWD and LSGD Roads-Pipeline Work
Project Code PTAJJM092115029P1
Type Package
Main Project Jal Jeevan Mission (JJM)-JJM : RWSS to Vechoochira Pt:-Laying of pumping/Gravity Mains to Sumps/GLSR/OHSR, providing Distribution Lines and 3950 FHTCs (Vechoochira-1600 nos, Naranamoozhi-350 nos, Pazhavangadi-2000nos) including restoration works of PWD and LSGD Roads-Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM : RWSS to Vechoochira Pt:-Laying of pumping/Gravity Mains to Sumps/GLSR/OHSR, providing Distribution Lines and 3950 FHTCs (Vechoochira-1600 nos, Naranamoozhi-350 nos, Pazhavangadi-2000nos) including restoration works of PWD and LSGD Roads-Pipeline Work
Status On-going
District Pathanamthitta
Executing Office Ranni Sn
Agreement Number
Agreement Date
TS Amount (Rs) 401600000
TS Number WRD/KWA-CE(SR)/EST_TS/17384/2022_26_1_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 21 Oct 2024
Expected date of Completion 21/10/2024

Processing Dates

TS Date 11 Mar 2023
Estimate Approval 11 Mar 2023
NIT Approval 11 Mar 2023
Tender Closing 26 Apr 2023
Technichal Pre-Qualification 27 Apr 2023

Approval Dates

Workorder Date 22 May 2022
NA 20 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Ranni PH Sn - AE
Date: 29/06/2024

Work in progress | 10% Completed

FHTC work ongoing.

Ranni PH Sub Dn - AEE
Date: 25/06/2024

Work in progress | 10% Completed

FHTC work ongoing.