| Attingal WS Dn EE |
| Date: 17/09/2021 |
Work has been completed | 100% Completed
Fund request given
| Attingal WS Dn EE |
| Date: 15/06/2021 |
Work has been completed | 100% Completed
Work completed and bill submitted.
| Attingal WS Dn EE |
| Date: 14/06/2021 |
Work has been completed | 100% Completed
Trial run completed.
| Attingal WS Dn EE |
| Date: 13/06/2021 |
Work has been completed | 100% Completed
Trial run completed.
| Attingal WS Dn EE |
| Date: 12/06/2021 |
Work in progress | 99% Completed
Work comnpleted , Trial run can be done.
| Attingal WS Dn EE |
| Date: 11/06/2021 |
Work in progress | 99% Completed
Work comnpleted , Trial run can be done.
| Attingal WS Dn EE |
| Date: 10/06/2021 |
Work in progress | 99% Completed
Work comnpleted , Trial run can be done.
| Attingal WS Dn EE |
| Date: 09/06/2021 |
Work in progress | 99% Completed
Work comnpleted , Trial run can be done.
| Attingal WS Dn EE |
| Date: 08/06/2021 |
Work in progress | 99% Completed
Work comnpleted , Trial run can be done.
| Attingal WS Dn EE |
| Date: 07/06/2021 |
Work in progress | 99% Completed
Errection work completed, Due to low voltage motor cannot work. Informed to KSEB.
| Attingal WS Dn EE |
| Date: 06/06/2021 |
Work in progress | 99% Completed
Errection work completed
| Attingal WS Dn EE |
| Date: 03/06/2021 |
Work in progress | 95% Completed
Electrical related works to be completed.
| Attingal WS Dn EE |
| Date: 02/06/2021 |
Work in progress | 95% Completed
Electrical related works to be completed.
| Attingal WS Dn EE |
| Date: 01/06/2021 |
Work in progress | 95% Completed
95 % completed.