State plan-2019-20 RWSS to Palachira- Supply erection and commissioning of 20HP submersible pumpset at Palachira pump house having discharge of 10 lps and head 100M

Project State plan-2019-20 RWSS to Palachira- Supply erection and commissioning of 20HP submersible pumpset at Palachira pump house having discharge of 10 lps and head 100M
Project Code TVMGOK06194878P1
Type Package
Main Project State plan-2019-20 RWSS to Palachira- Supply erection and commissioning of 20HP submersible pumpset at Palachira pump house having discharge of 10 lps and head 100M
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description Supply erection and commissioning of 20HP submersible pumpset at Palachira pump house having discharge of 10 lps and head 100M
Status On-going
District Thiruvananthapuram
Executing Office Varkala WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 356000
TS Number TS/2020-2021/2019/3333
Technical specification Supply erection and commissioning of 20HP submersible pumpset at Palachira pump house having discharge of 10 lps and head 100M

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 28/04/2021
Scheduled date of Completion as per agreement 02 Apr 2021
Expected date of Completion 05/05/2021

Processing Dates

TS Date 07 Dec 2020
Estimate Approval 03 Dec 2020
NIT Approval 16 Dec 2020
Tender Closing 26 Dec 2020
Technichal Pre-Qualification 29 Dec 2020
Price bid opening 29 Dec 2020

Approval Dates

Workorder Date 19 Feb 2021
NA 22 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Attingal WS Dn EE
Date: 17/09/2021

Work has been completed | 100% Completed

Fund request given.

Attingal WS Dn EE
Date: 15/06/2021

Work has been completed | 100% Completed

Work completed and bill submitted. .