| Sasthamcotta WS Sn 1 - AE |
| Date: 29/11/2023 |
Work has been completed | 100% Completed
Out of 73 /73 nos public tap disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 28/11/2023 |
Work in progress | 90% Completed
Out of 73 / 65 nos public tap disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 24/11/2023 |
Work in progress | 60% Completed
Out of 73 / 55 nos public tap disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 20/11/2023 |
Work in progress | 60% Completed
Out of 73 / 52 nos public tap disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 15/11/2023 |
Work in progress | 35% Completed
Out of 73 / 50 nos public tap disconnection completed
| Sasthamcotta WS Sn 1 - AE |
| Date: 10/11/2023 |
Work in progress | 20% Completed
Work in progress. 30 nos Public tap disconnection completed