| Project | DEPOSIT- RWSS To Kunnathoor - Balance Disconnection of public tap (73 Nos) in Kunnathoor Grama Panchayth |
|---|---|
| Project Code | KLMDEPO082314998P1 |
| Type | Package |
| Main Project | DEPOSIT- RWSS To Kunnathoor - Balance Disconnection of public tap (73 Nos) in Kunnathoor Grama Panchayth |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | DEPOSIT- RWSS To Kunnathoor - Balance Disconnection of public tap (73 Nos) in Kunnathoor Grama Panchayth |
| Status | On-going |
| District | Kollam |
| Executing Office | Sasthamcottah WS Sn1 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 124900 |
| TS Number | 14845/2023-2024 |
| Technical specification | DEPOSIT- RWSS To Kunnathoor - Balance Disconnection of public tap (73 Nos) in Kunnathoor Grama Panchayth |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 31/10/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Nov 2023 |
| Expected date of Completion | 30/11/2023 |
| TS Date | 25 Sep 2023 |
|---|---|
| Estimate Approval | 19 Sep 2023 |
| NIT Approval | 19 Sep 2023 |
| Tender Closing | 09 Oct 2023 |
| Technichal Pre-Qualification | 09 Oct 2023 |
| Price bid opening | 11 Oct 2023 |
| Workorder Date | 21 Oct 2023 |
|---|---|
| NA | 31 Oct 2023 |
| Sasthamcotta WS Sn 1 - AE |
| Date: 29/11/2023 |
Work has been completed | 100% Completed
Out of 73 /73 nos public tap disconnection completed .
| Sasthamcotta WS Sn 1 - AE |
| Date: 28/11/2023 |
Work in progress | 90% Completed
Out of 73 / 65 nos public tap disconnection completed .